1. Strip the sheath off the cable to leave the 
conductor with an L1 length exposed. Ensure 
that the value of L1 is equal to the tail length of 
the OT terminal.

2. Lead the cable through the heat shrink 
tubing and place the OT terminal on the 
exposed conductor.

Assembling the OT Terminal and the Power Cable

a

Appendix

Insulation layer of
the power cable

Heat shrink tubing

3. Use the crimping tool to crimp the joint parts 
of the bare crimping terminal and the 
conductor.

4. Install the heat shrink tubing.

Crimping tool

NOTICE

Heat the heat shrink tubing until it tightly clings to the 
connector. Do not overheat the heat shrink tubing, 
preventing the insulation layer being burnt.

The heat shrink tubing must be fixed to cover the 
cable conductor.

NOTICE

Ensure that the metal conductor of the cable is not 
damaged when stripping the sheath off the cable.

NOTICE

The contact terminal should contact the insulation sheath 
of the cable.
After the conductor is fed into the OT terminal, the 
protruding part of the conductor, L2 must not be longer 
than 2 mm. 

Содержание V100R005C10

Страница 1: ...lectrostatic damage to the subrack Only when the BBU install in TP48200A and APM30H cabinets subrack cable claws are configured Other cabinets carry on next step directly NOTE The figure shows only installation slots for the main processing board core network processing board baseband processing board fan module and power module in the typical configuration If you need to install the USCUb22 UEIU ...

Страница 2: ...inet interior using cable ties 2 Install a ground cable for the GPS SPD 3 Install a clock signal cable for the GPS SPD 1 Connect the N50 straight female connector of the clock signal cable to the PROTECT terminal on the GPS SPD using a torque wrench to a torque of 4 N m 2 Connect the SMA male connector of the GPS clock signal cable to the GPS port on the UMPT LMPT USCUb22 4 Connect the GPS SPD jum...

Страница 3: ...ler of an optical module and insert the optical module into the SFP0 SFP1 port on the LMPT the FE GE1 port on the UMPTb2 or the XGE1 XGE3 port on the UMPTe3 Then raise the puller 2 Remove the dustproof cap from the optical fiber Connect an FE GE optical fiber to the optical module 4 Install the winding pipe at the end of the optical fiber Ensure that the winding pipe is installed at the position b...

Страница 4: ...BBU cable claw positions 5 Install the winding pipe at the end of the optical fiber Ensure that the winding pipe is installed at the position between the optical fiber connector and the first optical fiber binding point The method is the same as that for installing an optical fiber Installing a GPS Clock Signal Cable 1 Connect the SMA end of the GPS clock signal cable to the GPS port on the UMPT L...

Страница 5: ...g to the network planning the boards in the BBU are inserted in the proper slots and secured 2 The subrack which is used to install the BBU is steady installed 3 According to the network planning the BBU cables are properly installed and secured 4 The GPS antenna must be installed in an area with an open view and far from high buildings The vertical view angle of the GPS antenna must be greater th...

Страница 6: ... power system The screws are tightened In addition the inputs or outputs are not short circuited 3 The redundant part of the power cable or PGND cable is cut rather than coiled 4 The terminals at two ends of each power cable or PGND cable are securely soldered or crimped 5 The bare wires and the terminal handles at the wiring terminals are coated with heat shrink tubing 6 A flat washer and a sprin...

Страница 7: ...of the bare crimping terminal and the conductor 4 Install the heat shrink tubing Crimping tool NOTICE Heat the heat shrink tubing until it tightly clings to the connector Do not overheat the heat shrink tubing preventing the insulation layer being burnt The heat shrink tubing must be fixed to cover the cable conductor NOTICE Ensure that the metal conductor of the cable is not damaged when strippin...

Отзывы: