eA380 Series LTE CPE
User Guide
3 Installation
Issue 01 (2017-08-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
37
Table 3-2
Hardware installation check of the eA380
No.
Check Item
1
The installation position must strictly comply with the design
drawings, meet the installation space requirements, and reserve space
for maintenance.
2
When the eA380 is mounted on a metal utility pole, the fixture must
be firmly installed, and the LTE CPE must be attached.
3
When the eA380 is mounted on the wall, the installation hole on the
fixture must be aligned with the one on the expansion bolt. In addition,
the fixture must be tightly and firmly attached to the wall and must not
wobble when you shake it.
When checking the cable connections of the eA380, check the items listed in Table 3-3 in
order.
Table 3-3
Cable connection check of the eA380
No.
Check Item
1
No cable is short-circuited or inversely connected.
2
The connector of the PoE network cable must be appropriately
connected.
The waterproof connector of PoE must be tightened.
Step 2
Perform the power-on check, as shown in Figure 3-17.