3 Commissioning Process
Airbridge BTS3606E&3606AE
System Commissioning Guide
3-28
Huawei Technologies Proprietary
Issue 02 (2006-10-10)
z
MS call test
z
Handoff test
z
Short message service test
z
Mobile-originated packet data call test
z
Mobile-terminated packet data call test
3.6.1 Location Update Test
The test procedure is as follows:
Step 1
Define a test MS in the HLR.
Step 2
Ensure that the network data is correctly configured.
Step 3
Switch on the MS.
Step 4
Start the Abis interface tracing on the BAM by using the LMT.
Step 5
Observe the signaling on the Abis interface and check if either of the following cases occurs:
z
The network side accepts the location update.
z
The network side rejects the location update request.
----End
3.6.2 BTS Coverage Test
The test procedure is as follows:
Step 1
Define a test CDMA MS in the HLR.
Step 2
Select a proper road to carry out a drive test in the BTS coverage area.
Step 3
Record test data, including:
z
Tested BTS
z
Coverage area
z
Sector
z
Distance
z
Signal strength and voice quality
Step 4
Check that the test result conforms to the requirements of engineering design documents.
----End
3.6.3 MS Call Test
The test procedure is as follows:
Step 1
Register two test MSs in the HLR.
Step 2
Power on the two MSs so that they connect to the network and they switch to idle mode.
Step 3
Carry out the following call tests.
z
Make a call from one MS to the other and hook on after the conversation.