SI No: N/A, Issue 2, 26 Jun 2017
1
Purpose
The purpose of the Assembly Procedure is to define a standard method for assembling and testing all
A2A SPACERS
.
This will ensure that each device is built in accordance with best practises and easily achieve the minimum
standards required for regulatory compliance.
2
Training Requirements
All personnel involved with assembling and/or testing this device must be trained against the latest version of
this Assembly Procedure.
3
Materials
As listed in drawing
Required documents
Works Order Route Card Containing Inspection History Card
Kitting list
Inspection and Release Procedure - P3060
Production Line Clearance - P3061
Clear Down Declaration Form - P3061(F)
4
Procedure
OP DEPT
OPERATION
10
10
ASSY
ASSY
Take a diaphragm (36071622) and pull 2 of the ends apart until the cut section fully opens.
Take clamp fingers moulding (36071612)
Assembly Procedure
Document Ref:
AP 3607157
Issue:
01
Issue Date:
19 December 2019
Page 1 of 21
Drawing:
Shown on works order
Description:
A2A SPACER AUSTRALIA
Issued by:
(Production Engineer)
O.Edoo
Signature:
Can be found on signed hard copy
Date
19/Dec/2019
Approved by:
(Production Manager)
A.
Ostacchini
Signature:
Can be found on signed hard copy
Date
19/Dec/2019