measurement tubes to an IT rack from one HPE Adaptive Rack Cooling System. Do not connect
multiple pickups to an IT rack from different HPE Adaptive Rack Cooling Systems. In the specific case
of an HPE Adaptive Rack Cooling System mounted at the end of an aisle with no IT racks to one side,
join the two pressure tubes for that HPE Adaptive Rack Cooling System with a tee and route it to the
farthest IT rack on the side of the HPE Adaptive Rack Cooling System that is cooled by that HPE
Adaptive Rack Cooling System, up to two racks away.
HPE Adaptive Rack Cooling System configured between two IT racks with each IT rack
receiving a pressure tube on the cold aisle side
HPE Adaptive Rack Cooling System configured between four IT racks with the pressure tubes
installed on the furthest outboard IT racks on either side
30
Installation