Figure 4-5 Wall Receptacle Pinouts
WARNING!
There is a risk of shock hazard while testing primary power. Use properly
insulated probes.
5.
Verify that the voltage between receptacle pins x and y is between 200 and 240 V AC.
6.
Set the site power circuit breaker to
Off
.
7.
Ensure that power is removed from the server.
8.
Route and connect the server power connector to the site power receptacle.
•
For locking type receptacles, line up the key on the plug with the groove in the receptacle.
•
Push the plug into the receptacle and rotate to lock the connector in place.
WARNING!
Do not set site AC circuit breakers serving the processor cabinets to
On
before
verifying that the cabinet has been wired into the site AC power supply correctly. Failure
to do so might result in injury to personnel or damage to equipment when AC power is
applied to the cabinet.
9.
Set the site power circuit breaker to
On
.
10. Set the server power to
On
.
11. Check that the indicator light on each power supply is on.
MP Core I/O Connections
Each HP 9000 rp7420 server can have up to two MP core I/O board sets installed. Which allows
two partitions to operate, or MP core I/O redundancy in a single partition configuration. Each
MP core I/O board set consists of two boards: the MP/SCSI board and the LAN/SCSI board. The
MP/SCSI board is oriented vertically and accessed from the back of the server. The LAN/SCSI is
accessed from the PCI/PCI-X expansion card bay. Only the primary MP core I/O board set
(MP/SCSI slot 1 and LAN/SCSI slot 8, chassis 1) is required for a single partition implementation.
The secondary MP/SCSI board is not necessary for full operation. However, without the secondary
MP/SCSI board, only two internal disks can be accessed.
MP/SCSI Connections
The MP/SCSI board is required to update firmware, access the console, turn partition power on
or off, access all but two of the internal peripherals, and use other features of the server.
Connections to the MP/SCSI board include the following:
MP Core I/O Connections
55
Содержание rp7420
Страница 3: ......
Страница 4: ......
Страница 12: ...12 ...
Страница 16: ...16 ...
Страница 30: ...Figure 1 12 Left Rear View of HP 9000 rp7420 server 30 Overview ...
Страница 40: ...40 ...
Страница 50: ...50 ...
Страница 82: ...82 ...
Страница 106: ...Figure 6 25 Front Panel Board Cable Location on Backplane 106 Removing and Replacing Server Components ...
Страница 108: ...108 ...
Страница 119: ...Figure D 3 Planning Grid Computer Room Layout Plan 119 ...
Страница 120: ...Figure D 4 Planning Grid 120 Site Preparation Guidelines ...
Страница 121: ...Figure D 5 Planning Grid Computer Room Layout Plan 121 ...
Страница 122: ...Figure D 6 Planning Grid 122 Site Preparation Guidelines ...
Страница 123: ...Figure D 7 Planning Grid Computer Room Layout Plan 123 ...
Страница 124: ...124 ...
Страница 127: ...X XD 115 127 ...