5 Radius Configuration
6 Modbus/TCP Configuration
7 Settings Ethernet Port >Auto<
8 System Name > HPE Adaptive Rack Cooling System<
9 System Contact >Your administrator<
A System Location >Room 123 Building ABC<
B Actual Date >26.02.1970<
C Actual Time >20:08:41<
D Beeper >Disabled<
E Security
F SNMP Configuration
G Reboot Unit >No<
ESC=End
IPv4 Configuration
Baying the racks together
Use the foam gasket included in the HPE ARCS Air Rack Accessory Kit and the sealing tape included in
the HPE ARCS Air Rack Installation Kit to bay the HPE Adaptive Rack Cooling System and HPE ARCS
42U/48U 600x1600mm Racks together to prevent loss of air pressure within the system. Start the
installation at the HPE Adaptive Rack Cooling System and work outwards in both directions to the end of
the row.
For more information on accessory and option kits, see
Accessory and option kit contents
.
On the HPE Adaptive Rack Cooling Unit:
1.
If the HPE Adaptive Rack Cooling System is on the end of a row, to seal around the panels, apply
sealing tape as indicated.
2.
If the HPE Adaptive Rack Cooling System is bayed to an adjacent rack, apply the foam gasket in the
corners of the frame.
3.
If the HPE Adaptive Rack Cooling System is bayed to an adjacent rack, apply the foam gasket around
the perimeter. To separate high and low pressure, apply one central vertical strip of foam gasket.
18
Configuration
Содержание Adaptive Rack Cooling System
Страница 46: ...The installation is complete 46 Configuration ...