8 Operation
8.1 Initial commissioning
Caution
Risk of damage to property as a result of performing initial commissioning
on your own authority. Initial commissioning must be performed by the
manufacturer’s customer service technicians .
Preparing for initial commissioning:
Checklist:
■
Have all the media connections been made (electric cabling, water piping,
condensate drain and air duct connections)?
■
Is the heating medium or cooling medium available?
■
Are the hydraulics aligned and balanced?
■
Are all the control components installed and wired?
■
Are all of the respective trade groups (installer, electrician, etc.) present at the
scheduled time?
■
Are the system operating personnel present for training at the scheduled time?
8.2 Operation
The system runs fully automatically depending on the programmed operating
times and temperature conditions.
■
Observe the operating instructions for the control system.
■
Check alarm displays daily.
■
Correct changes to operating times in the programming accordingly.
■
Ensure free air outlet and unhindered dispersion of the supply air.
■
For applications with oil-saturated extract air: Do not operate the units in
'Recirculation' mode (REC) unless there is no oil pollution in the room.
■
For applications with high extract air humidity: Do not operate the units unless
icing protection is provided.