5895XL Manual - P/N 151142-L8:L 08/09/2017
Hardware Installation
AC Power
Section 3: Hardware Installation
5895XL installation involves the following steps:
•
AC power (Section 3.1) and backup battery connection (Section 3.2).
•
Physical connection to the FACP or to the controlling 5895XL (see Section 3.3).
•
Setting an ID for the 5895XL (Section 3.3.1).
•
Physical connection of SBUS modules that will be powered by this 5895XL (Section 3.4).
•
Physical connection of any outputs (conventional relays, notification appliances, auxiliary power modules, and so on) that will be
powered by this 5895XL. See Section 3.5.1 for notification appliance wiring information. Refer to the FACP Installation Manual,
for software configuration information and other information about installing outputs.
3.1 AC Power
At installation, connect the AC terminals to 120 VAC source as shown in Figure 3.5. It may be necessary for a professional electrician to
make this connection.
The AC terminals are rated as 120 VAC, 50 or 60 Hz, 2.7 A.
Figure 3.5 AC Power Connection
3.2 Battery Connection
The 5895XL battery charge capacity is 7.0 to 33.0 AH. Use 12V batteries of the same AH rating. Determine the correct AH rating as per
your current load calculation (see Section Table 2.4 or Table 2.5).
* 33AH max battery size for FM (Factory Mutual) installations
Model Number
FACP Installation Manual
5820XL/EVS
LS10061-001SK-E
6820/EVS
LS10144-001SK-E
5700
151295
6700
LS10148-001SK-E
5808
151274-L8
6808
LS10146-001SK-E
To 120 VAC
Power Source
Gr
een
Wh
ite
Black
NOTE:
When your backup batteries requirements use backup batteries that are to large to fit into the 5895XL cabinet. The AB-33 cabinet
holds batteries up to the 33 AH size. (Refer to FACP Installation Manual for AB-33 installation instructions.