6. Maintenance

6.1. General

The machine and the entire system must be inspected 
and maintained at regular intervals. The time limit for 
maintenance is set by the manufacturer and applies to 
the general conditions of use. The manufacturer should 
be consulted if the system is to be used with corrosive 
and/or abrasive pumped liquids, as the time limit between 
inspections may need to be reduced. 

Note the following information:

• 

The operating and maintenance manual must be 
available to the maintenance personnel and its in-
structions followed. Only the repair and maintenance 
measures listed here may be performed.

• 

All maintenance, inspection and cleaning work on the 
machine and the system may only be carried out by 
trained specialists exercising extreme care in a safe 
workplace. Proper protective clothing is to be worn. 
The machine must be disconnected from the electric-
ity supply before any work is carried out. There must 
be no way that it can be inadvertently switched on. 
Additionally, the appropriate protective measures as 
defined by the BGV/GNV should be enforced when 
working in basins and/or containers.

• 

Above a weight of 50kg, only hoisting gear which has 
been officially approved and which is in a technical-
ly perfect condition should be used for lowering and 
raising the machine.

Make sure that all fastening devices, ropes and safety 
devices of the hand winch are in a technically perfect 
condition. Work may only commence if the auxiliary 
hoisting gear has been checked and found to be in 
perfect working order. If it is not inspected, danger to 
personnel may result!

• 

Wiring work on the machine and system must be 
carried out by an electrician. For machines approved 
for work in areas subject to explosion danger, please 
refer to the “Explosion protection in accordance with 
the regulation” chapter. 

• 

When working with inflammable solvents and clean-
ing agents, fires, unshielded lighting and smoking are 
prohibited.

• 

Machines which circulate fluids hazardous to health, 
or which come into contact with them, must be de-
contaminated. It must be ensured that no dangerous 
gases can form or are present.

• 

Ensure that all necessary tools and materials are 
available. Tidiness and cleanliness guarantee safe and 
problem-free operation of the machine. After work-
ing on the machine all cleaning materials and tools 
should be removed from it. All materials and tools 
should be stored in an appropriate place.

• 

Operating supplies such as oil and lubricants must 
be collected in appropriate vessels and properly dis-
posed of (in accordance with the 75/439/EEC direc-
tive and with §§5a, 5b AbfG). Appropriate protective 
clothing is to be worn for cleaning and maintenance 
jobs. This is to be disposed of in accordance with 
waste code TA 524 02 and EC Directive 91/689/EEC.  
 

Only lubricants expressly recommended by the 

 

manufacturer may be used. Oils and lubricants should 
not be mixed. Only use genuine parts made by the 
manufacturer.

A trial run or functional test of the machine must be 
performed as instructed in the general operating con-
ditions.

Oil type

: degradable HOMA-Atox. Used oil is to be dis-

posed accordingly.

When using white oil, note the following:

• 

The machine lubricants may only be topped up or re-
placed with lubricants from the same manufacturer.

• 

Machines which have previously been operated us-
ing other lubricants must first be thoroughly cleaned 
before they can be operated using white oil. 

6.2. Maintenance intervals

Before initial start-up or after a longer period of 

 

storage:

• 

Checking the insulation resistance

• 

Fill level check in sealing room/chamber 

• 

The axial face seal must be checked for damage.

Monthly:

• 

Monitoring the current consumption and voltage

• 

Checking the used relays for posistors, sealing room 
monitor, etc.

Every six months:

• 

Visual inspection of the power supply cable

• 

Visual inspection of the cable holder and the cable 
bracing

• 

Visual inspection of accessories, e.g. the suspension 
device and hoisting gears

1,000 operating hours or after every six months, whi-
chever is earlier:

• 

Monitoring the current consumption and voltage

• 

Checking the used relays for posistors, sealing room 
monitor, etc.

• 

Visual inspection of the power supply cable

• 

Visual inspection of the cable holder and the cable 
bracing

• 

Visual inspection of accessories, e.g. the suspension 
device and hoisting gears

3,000 operating hours:

• 

Visual control at pump types with oil chamber

• 

Visual control at pump types without oil chamber

Содержание KX...H series

Страница 1: ...Original Betriebsanleitung EN Original Instruction Manual NL Originele handleiding KX H...

Страница 2: ...g Transport und Lagerung 11 4 1 Anlieferung 11 4 2 Transport 11 4 3 Lagerung 11 4 4 R cklieferung 12 4 5 Abladen von gro en Pumpen 12 4 6 Transportsicherung 13 5 Aufstellung und Inbetriebnahme 13 5 1...

Страница 3: ...ll schutz und zur Unfallverh tung Diese Betriebsanleitung muss dem Bedienpersonal jederzeit am Einsatzort des Produktes verf gbar sein 1 3 Bestimmungsgem e Verwendung Die HOMA Produkte entsprechen den...

Страница 4: ...ese Vereinbarungen laufen mindes tens bis zum vereinbarten Ende der Gew hrleistungszeit des Produktes 1 5 2 Ersatzteile An und Umbauten Es d rfen nur Originalersatzteile des Herstellers f r Reparatur...

Страница 5: ...ltdauer und die Spieldauer falls sie von 10 min abweicht Beispiel S3 30 bedeutet dass die Maschine 3 Minuten betrieben werden kann und anschlie end 7 Minuten abk hlen muss Schl rfbetrieb Der Schl rfbe...

Страница 6: ...Ma nahmen zu ergreifen damit sich keine Personen unter h ngenden Lasten aufhalten k nnen Weiterhin ist es untersagt h ngende Lasten ber Arbeitspl tze zu bewegen an denen sich Personen aufhalten Beim...

Страница 7: ...tmosph re geeignet F r diesen Einsatz m ssen die Pumpen bestimmte Richtlinien erf llen Ebenso m ssen bestimmte Verhaltensregeln und Richtli nien vom Betreiber eingehalten werden Pumpen welche f r den...

Страница 8: ...der Oberkante des Pumpengeh uses liegen Bei Nassaufstellung ohne K hlmantel muss das Motorgeh use immer komplett untergetaucht sein Die Temperatur des F rdermediums darf bis 40 C betra gen kurzfristig...

Страница 9: ...ften umzusetzen Zu beachten Die Bedingungen am Einsatzort m ssen allen Leistungs schildangaben entsprechen Bei Unklarheiten muss vor Inbetriebnahme R cksprache mit dem Herstellerwerk gehalten werden 3...

Страница 10: ...nie in die Pumpenkammer oder an die drehenden Teile greifen Vor Wartungs oder Reparaturarbeiten die Maschine abschalten und die drehenden Teile zum Stillstand kommen lassen Au erdem ist es m glich di...

Страница 11: ...henden Gase bzw Strahlungen die Elasto merteile und Beschichtungen angreifen k nnen Bei Produkten mit Saug und oder Druckanschluss sind diese fest zu verschlie en um Verunreinigungen zu verhindern All...

Страница 12: ...en sinngem en Zweck Wenn Sie diese Regeln beachten kann Ihr Produkt ber einen l ngeren Zeitraum eingelagert werden Beachten Sie aber dass die Elastomerteile und die Beschichtungen einer nat rlichen Ve...

Страница 13: ...teuerungen ist auf die mindest Wasser berdeckung zu achten Lufteinschl sse im Pumpengeh use und in Rohrlei tungen sind unbedingt zu vermeiden durch geeigne te Entl ftungseinrichtungen oder ein leichte...

Страница 14: ...t von der Rohrkonsole verwenden die F hrungsrohre m ssen genau senkrecht stehen Kupplungsfu mit Schwerlastd beln am Schachtboden befestigen Auf genau waagerechte Position des Kupplungsfu es achten Bei...

Страница 15: ...die Kette und heben Sie die Pumpe lang sam und kontrolliert an Schwenken Sie die Pumpe anschlie end ber den Betriebsraum und senken sie vorsichtig ab Bei Verwendung einer Einh ngevorrichtung Beach te...

Страница 16: ...re chenden rtlichen und VDE Vorschriften einzuhalten Der Motor muss durch einen Motorschutzschalter gesch tzt werden Lassen Sie den Motor gem dem Schaltplan anschlie en Achten Sie auf die Drehrichtung...

Страница 17: ...der Nennspannung laut Typenschild einzustellen Betrieb mit Frequenzumrichter Die Maschine kann an Frequenzumrichter betrieben wer den Beachten Sie hierf r das Kapitel 5 9 dieser Betriebs anleitung Ein...

Страница 18: ...igte Werkzeug und Material vorhanden ist Ordnung und Sauberkeit ge w hrleisten ein sicheres und einwandfreies Arbeiten an der Maschine Entfernen Sie nach dem Arbeiten gebrauchtes Putzmaterial und Werk...

Страница 19: ...Kabelhalter Karabinerhaken und der Seilabspannung Zugseil Beim Einsatz der Maschine in Becken bzw Sch chten sind die Hebeseile Kabelhalter Karabinerhaken und die Seilabspannung einem stetigen Verschl...

Страница 20: ...icewerkstatt durchgef hrt werden Betriebsmittelwechsel Das abgelassene Betriebsmittel muss auf Verschmut zungen und Wasserbeimengungen kontrolliert werden Ist das Betriebsmittel stark verschmutzt und...

Страница 21: ...befestigung Zylinderschraube mit Innensechskant l sen und herausdrehen Achten Sie auf die Schraubensicherung Das Laufrad mit einem geeigneten Abzieher von der Welle abziehen Welle reinigen Neues Laufr...

Страница 22: ...tomerteilen und der Geh usebeschichtung vorzubeugen Bei Einlagerung in Werkst tten beachten Die Strah lung und die Gase die beim Elektroschwei en ent stehen zerst ren die Elastomere der Dichtungen Bei...

Страница 23: ...gen und oder Festk rper abgebremst erh hte Stromaufnahme Maschine abschalten gegen Wiedereinschalten sichern Laufrad Propeller gangbar machen bzw Saugstutzen reinigen Dichte des Mediums ist zu hoch R...

Страница 24: ...ggf Gummikompensatoren verwenden Leckage der Gleitringdichtung Dichtraumkontrolle meldet St rung bzw schaltet die Maschine ab Ursache Abhilfe Erh hte Leckage beim Einlauf neuer Gleitringdichtungen lw...

Страница 25: ...DEUTSCH 25 Notizen Notes...

Страница 26: ...age 35 4 1 Delivery 35 4 2 Transport 35 4 3 Storage 35 4 4 Returning to the supplier 36 4 5 Unloading of big pumps 36 4 6 Locking device 36 5 Installation and initial commissioning 37 5 1 General 37 5...

Страница 27: ...at all times and also be made available where the product is used 1 3 Proper use The HOMA products comply with the valid safety regu lations and meet the demands of state of the art tech nology In the...

Страница 28: ...ufactur er may be used for repairs replacements add ons and conversions Only these parts guarantee a long working life and the highest level of safety These parts have been specially designed for our...

Страница 29: ...uct on or off depending on the filling level This is made possible by installing a float switch 2 Safety This chapter lists all the generally applicable safety instruc tions and technical information...

Страница 30: ...connec tion data sheet must be observed when connecting the product The technical specifications must be strictly adhered to If the machine has been switched off by a protective device it must not be...

Страница 31: ...s e g suspension unit and pipeline operating site immersion depth etc Once the product has been in stalled we recommend that the operator make additional measurements under all operating conditions Ca...

Страница 32: ...rged in pumped liquid at least up to the top edge of the pump or motor housing The mo tor housing must always be completely submersed for wet installation without a water jacket The temperature of the...

Страница 33: ...ust conform to all de tails on the rating plate In the case of uncertainty the manufacturer must be con sulted before commissioning 3 3 2 Motor The three phase asynchronous motor is made from sheet me...

Страница 34: ...t cooling jacket or U version with cooling jacket and open cooling circuit If the shaft seal on the medium side leaks water enters the oil chamber and changes the resistance of the oil The conductivit...

Страница 35: ...tly 4 3 Storage Newly supplied products are prepared that they can be stored for 1 year The product should be cleaned thor oughly before interim storage The following should be taken into consideratio...

Страница 36: ...tions on filling Damaged coatings should be repaired immediately Only a coating that is completely intact fulfills the criteria for intended usage If these rules are observed your product can be store...

Страница 37: ...tening of the pump The operator is responsible for this A dry run is strictly prohibited We recommend a level control for that Use baffles for the inlet This prevents air entry into the pumping medium...

Страница 38: ...off to the pressure line and is ready for operation Hang the end of the discharge chain from a hook at the shaft opening Hang the motor connection cable of the pump in the shaft at an appropriate len...

Страница 39: ...must be re moved before lowering or immersion into the pumping medium Please check the following points Cable routing no loops slightly taut Liquid temperature and immersion depth check see machine d...

Страница 40: ...otherwise be dam aged and leak In addition it must be ensured that the minimum flow rate is not less than 0 7 m s 5 10 Types of startups Types of startup using with cables with exposed ends Star Delta...

Страница 41: ...esent Ensure that all necessary tools and materials are available Tidiness and cleanliness guarantee safe and problem free operation of the machine After work ing on the machine all cleaning materials...

Страница 42: ...ear Regular inspections are nec essary in order to prevent the lifting cables cable holders carabiners and or cable bracing from wearing out and to prevent the electricity cable from being damaged The...

Страница 43: ...there are several versions and designs of these mo tors the exact location of the screw plugs varies depend ing on the pump unit used Slowly and carefully remove the filling plug from the sealing room...

Страница 44: ...monthly to quarterly function run for a period of 5 minutes Caution Only carry out a function run under the proper con ditions of operation and use Never run the machine dry This can result in irrepar...

Страница 45: ...e sensors option has interrupted the power circuit operator related See fault Mechanical shaft seal leaks sealing chamber monitor reports fault and switches the machine off Machine runs but does not p...

Страница 46: ...d Clean the suction port strainer and or impeller Propeller The impeller is blocked Switch off the machine secure it against being switched on again and free the impeller Inadmissible levels of gas in...

Страница 47: ...English 47...

Страница 48: ...ansport 57 4 3 Opslag 58 4 4 Retourneren 58 4 5 Lossen van grote pompen 58 4 6 Transportbeveiliging 59 5 Opstelling en inbedrijfstelling 59 5 1 Algemeen 59 5 2 Installatie 60 5 3 Toepassing van kettin...

Страница 49: ...preventie en of breidt deze uit Deze handleiding moet altijd beschikbaar zijn voor het bedie ningspersoneel op de werkplek van het product 1 3 Beoogd gebruik De HOMA producten voldoen aan de geldende...

Страница 50: ...afspraken lopen ten minste tot aan het overeengekomen einde van de wettelijke garan tietermijn van het product 1 5 2 Onderdelen aan en ombouwwerkzaamheden Er mogen uitsluitend originele onderdelen va...

Страница 51: ...wordt een gelijkblijvende temperatuur bereikt die ook bij langer bedrijf niet meer stijgt Het materieel kan ononderbroken onder nominale belasting werken zonder dat de toegestane temperatuur wordt ov...

Страница 52: ...onmiddellijke stilzetting door de bediener is dwin gend noodzakelijk wanneer er gebreken optreden die de veiligheid in gevaar brengen Hieronder vallen Falen van de veiligheids en of bewakingscontro le...

Страница 53: ...eel is verantwoordelijk voor de nale ving van de voorschriften Tijdens het bedrijf draaien bepaalde onderdelen waaier propeller om de vloeistof te verpompen Door bepaalde bestanddelen kunnen er aan de...

Страница 54: ...MA verpompen huishoudelijk gemeen telijk en industrieel afvalwater fecali n en slib ook met hoge aandelen vaste stoffen en vezels evenals alle soor ten vuilwater Van kleine woon of industri le gebouwe...

Страница 55: ...24 Cos phi Cos phi 25 Beschemingsklasse Beschemingsklasse 26 Vermogen P2 Vermogen P2 27 Bedrijfswijze Bedrijfswijze 28 Tekstveld Verkoop Ex goedkeuringsnummer 29 Ex onderzoekslaboratorium 30 Ex marker...

Страница 56: ...uurvoelerset in de motorwikkelingen Bij pompen in normale uitvoering worden de aansluitin gen van de temperatuurvoelers via de aansluitkabel naar buiten geleid en moeten deze via de adereinden T1 en T...

Страница 57: ...het lagerhuis en de drukdeksel die samen de met medicinale witte olie gevulde afdichtingskamer vormen De inspectieschroef op het lagerhuis en een optionele elektronische bewaking bieden controlemogel...

Страница 58: ...Gevaar door elektrische stroom Door beschadigde stroomtoevoerkabels dreigt levensgevaar Defecte leidingen moeten onmiddel lijk door een gekwalificeerde elektricien worden vervangen Pas op voor vocht...

Страница 59: ...aargelang kabelleng te en gewicht moet er om de 2 3 m een kabelhouder worden aangebracht De fundering constructie moet voldoende sterkte hebben voor een veilige en effectieve bevestiging van de pomp H...

Страница 60: ...etlood van de leidingconsole gebruiken de geleidestangen moeten exact verticaal staan Koppelingsvoet met ankers voor zware belasting aan de putbodem be vestigen Let op een exact horizontale positie va...

Страница 61: ...stabiel staat en of het koppelingssys teem correct vastgekoppeld is Verwijder de ketting uit het hijswerktuig en bevestig deze aan de kettingzekering die zich aan de boven rand van de bedrijfsruimte...

Страница 62: ...v controle van de afdichtkamer aangesloten en op werking gecontroleerd worden Gevaar door elektrische stroom Door ondeskundige omgang met stroom bestaat le vensgevaar Alle pompen met vrije kabeluitein...

Страница 63: ...orden gecontroleerd en onderhouden De periode voor het onderhoud wordt door de fabrikant vastgelegd en geldt voor de algemene gebruiksvoorwaarden Bij agres sieve en of abrasieve vloeistoffen moet over...

Страница 64: ...angen van bedrijfsvloeistof afdichtruimte kamer Controle en evt herstel van de coating Functietest van alle veiligheids en bewakingscontro les 15 000 bedrijfsuren of uiterlijk na 5 jaar Groot onderhou...

Страница 65: ...an de veiligheids en bewakingscontroles Bewakingscontroles zijn bijv temperatuurvoelers in de motor controle van de afdichtkamer motorbeschermings relais overspanningsrelais etc Motorbeschermings en o...

Страница 66: ...schillende pomponderdelen Waaier en pomphuis vervangen De cilinderschroef met binnenzeskant van afdichthuis losdraaien en eraf draaien Het pomphuis met geschikte hulpmiddelen borgen bijv hulphijswerkt...

Страница 67: ...coating van het huis te voorkomen Let bij opslag in werkplaatsen op het volgende De straling en de gassen die bij het elektrisch lassen ont staan vernielen het elastomeer van de afdichtingen Bij lange...

Страница 68: ...verstoppingen en of vaste delen afgeremd verhoogd stroomverbruik Machine uitschakelen beveiligen tegen opnieuw inschakelen zorgen dat waaier propeller kan draaien of zuigopening reinigen Dichtheid va...

Страница 69: ...oren gebruiken Lekkage van de glijringafdichting controle van de afdichtkamer meldt storing of schakelt de machine uit Oorzaak Oplossing Verhoogde lekkage bij de inlaat van nieuwe glijringafdichtingen...

Страница 70: ...70 Notizen Notes...

Страница 71: ...71 Notizen Notes...

Страница 72: ...bedingte Kontaminierung des Ger tes toxisch nein ja welche Stoffe tzend nein ja welche Stoffe mikrobiologisch nein ja welche Stoffe explosiv nein ja welche Stoffe radioaktiv nein ja welche Stoffe sons...

Страница 73: ...the instruments toxic no yes substance corrosive no yes substance microbiological no yes substance explosive no yes substance radioactive no yes substance other substances no yes substance Legally bi...

Страница 74: ...tourneren Contaminatie van het apparaat als gevolg van de toepassing giftig nee ja welke stoffen bijtend nee ja welke stoffen microbiologisch nee ja welke stoffen explosief nee ja welke stoffen radioa...

Страница 75: ...75...

Страница 76: ...x 49 0 2247 702 44 e Mail info homa pumpen de Internet www homa pumpen de Industriestra e 1 53819 Neunkirchen Seelscheid Telefon 49 0 2247 702 0 Fax 49 0 2247 702 44 e Mail info homa pumpen de Interne...

Отзывы: