1
4
Operation manual monty 3300/2-speed/GP
Installation of the machine
3
4
=
=
500
~
Fit the machine post using through shaft, bushings,
washers, and nuts (Fig. 2A, Item 1).
When laying the pneumatic hose
fully pull out the
mounting arm
so that the pneumatic hose is allowed
enough length for operation and will not break.
Tilt the machine post and pull up the rod (Fig. 2A, Item 9).
Connect the rod to the machine post with the lock pin
(Fig. 2A, Item 7) and cotter pin (Fig. 2A, Item 8).
Fit cover plate (Fig. 2A, Item 13) using the screw.
Fit the lateral panel of the housing.
When first setting the machine into operation, check
hose connections and unions for leakage.
2.3
Transporting the machine at site
Suitable lifting cables and lifting facilities or a fork-lift truck
should be used for transporting the machine. Always mind the
centre of gravity of the machine.
Fig. 3
Transport using a fork-lift truck
For transport of the machine secure machine post and
mounting arm against moving out of place.
Tilt the machine slightly.
Drive the fork-lift truck below.
Lower the machine on the fork-lift truck and position such
that it will not turn over during transport (mind the centre
of gravity of the machine).
Fig. 4
Transport using lifting facilities
For transport of the machine secure machine post and
mounting arm against moving out of place.
Position the lifting cables or other suitable lifting facilities
on the machine as illustrated in Fig. 4.
When lifting the machine, make sure that the lifting
cables are properly positioned (mind the centre of gravity
of the machine) and that the machine does not turn over.