After this, align the entire MSH Basic-FUBO-E-SR4 together
with the FUBO-FIX using a spirit level.
In doing so, set the adjustable ground spikes to unfinished
floor height using the side marking
("Upper edge unfi-
nished floor height" – RFB)
of the MSH Basic-FUBO-E-
SR4 (see Fig.: 32).
•
Finally, check all measurements in order to
observe wall clearance.
Recommended wall clearance: at least 50 mm
(see Fig.: 33).
•
On the MSH Basic-FUBO-E-SR4 there is a la-
bel/marking:
"Upper edge unfi nished fl oor
height"
. When correctly positioned, the upper
edge of the wall sleeve stands approx. 190 mm
above the unfi nished fl oor (RFB). The system
allows shortening of the wall sleeve by 150
mm to fi nished fl oor height later.
5
1
3
4
2
21 Description of the pipe bends RB1000/DN150 respectively RB1000/DN200
Legend for Fig.: MSH Basic-FUBO-FIX with pipe bends RB1000/DN150
1
Wall sleeve (partially coated)
2
Fastening bow incl. centring wedge
3
Pipe bend RB1000/DN150
4
Installation fi xture MSH Basic-FUBO-FIX
Fig.: Pipe bends RB1000/DN150