Preliminary Checks
HEADROOM
INCLUDED PARTS
TOOLS REQUIRED
Before beginning installation, ensure that there is an 85-inch vertical clearance top and
bottom for the lift.
Before beginning installation, inspect and check the box contents. Report any damage to your
dealer. Parts are packed on a long skid. Skid will contain the following:
• Cordless drill
• Phillips screwdriver (#3)
• 6-10” driver extension
• Level (3’ and 4’)
• SAE socket set
• Allen wrench (5/64”, 5/32”, 3/16”, 5/16”)
• Nut driver (3/8” and 5/16”)
• T30 Torx bit (included)
• Hack saw or chop saw
• Tape Measure
• Volt meter
• Hammer
Chassis Box:
• Chassis
• Call/send parts
• 2 Call/send hand controls
• Power Supply
• Manual Hand Crank
• Installation Manual
• Owner's Manual
Rail Bracket Box
• Rail brackets (2, 3, 4, or 6
per set)
• Wood screws (#14 X 2” (4
per rail bracket)
Upper Guide Rail
Platform
Unit Box
Rail Box:
• Bottom rail pre-installed with:
• Bottom end plate
• Charge strip wire harness
• Bottom limit cam
• Joint pins and joint brackets
(two-piece rail only)
• Plastic gear rack
• Top rail pre-installed with:
• Charge strip wire harness
• Rail accessories (plastic bag):
• Top end plate
• Compression bolts (2 sizes)
• Self-cutting screws
(1/4”-20 X 1”)
• Torx T30 driver bit
• Rail parts (plastic bag):
• Extra plastic racks
(2 or 3)
• Top limit cam