background image

 
HAMWORTHY HEATING LTD 

 

WESSEX-HE 200 BOILER 

 

500001008/K 

11 

11.0 COMMISSIONING AND TESTING 
 
11.1 Electrical Installation 
 

For design see Section 9. 
 
A suitably competent person must check wiring. 
 
Normal supply required is 230V 50Hz single phase.  
An isolator correctly fused at 5 Amperes should be 
sited close to the boiler. 
 
Any other interlocks i.e. pressurisation unit, BEM 
system should be wired in series with the remote 
stop/start loop (C5 & C6). 
 
A schematic of the circuit is shown in Figure No. 5. 
 

11.2 Gas Installation 
 

For design see Section 5. 
 
The whole of the gas installation including the meter, 
must be inspected and tested for soundness and 
purged, in accordance with the recommendations of 

BS 6891, UP/1

 or 

UP/1A

 as appropriate. 

 

11.3 Water Circulation System 
 

For design see Section 8. 
 

NOTE!

  If a boiler is to be fitted into an old or existing 

pipework system it is advisable that this is chemically 
cleaned and thoroughly flushed prior to installation. 
 
The whole of the system should be thoroughly 
flushed out with cold water without the pump in 
position.  Ensure that all valves are open. 
 
With the pump fitted, the system should be filled and 
air locks cleared.  Vent the heat emitters and check 
for leaks. 
 

11.4 Lighting the Boiler (Initial Commissioning) 
 

Prior to delivery, all Wessex boilers are subject to a 
full sequence check and the differential pressure 
switch is adjusted to design settings (See Section 
2.2). The intent therefore of the following initial 
commissioning procedure, is to check the correct 
functioning of the sequence system up to and 
including the establishment of the pilot flame, with the 
gas supply to the main burner isolated. 
 

WARNING:

  Before attempting to light the boiler 

ensure that any personnel involved are aware of what 
action is about to be taken and begin by making the 
following checks: - 
 
i) Flueway passages and chimney are clear of 
obstructions. 
ii) Adequate ventilation exists in the boiler house, 

reference Section 7. 
iii) The system is fully charged with water, ready to 
receive heat, all necessary valves are open and the 
pump is running and circulating the water. 
iv) The pipework and valve arrangement is installed 
to Hamworthy recommendations in such a way that 
adequate water flow rates will be present in 
accordance with Figure No. 3. 
v) The gas supply pipework is clear of any loose 
matter, tested for soundness and purged. 
 
Turn off the electrical supply to the boiler at the mains 
external isolator. 
 
a) Remove the boiler front cover. 
 
Disconnect the main gas valve wiring assembly plug, 
thus isolating the gas valves from the main burner 
controller. 
 
Remove wire link on terminals C1 & C2 and insert a 
Multi-Meter set to read DC µA. 
 
Ensure main gas supply is turned 

ON

 at the boiler 

manual shut-off valve (Reference Figure No. 6.). 
 
Remove the blank plug from the temperature limit 
reset panel on the fascia and push in the exposed 
reset button.  Replace plug. 
 
Set the control thermostat to the minimum setting 
(65

o

C) and switch on the electrical supply to the boiler 

at the external isolator, ensuring that all external 
controls are calling for heat (e.g. time clocks etc.). 
 
b) Switch the boiler ON/OFF switch to ‘ON’. Re-set 
the controller if at lockout, the cam timer will run to its 
normal start position. The fan will then start and the 
boiler will pre-purge for approximately 40 seconds. 
 
c) Following this pre-purge period, an ignition spark 
will be generated and the pilot gas solenoid valve will 
energise to supply gas to the pilot burner. 
 
d) After a few seconds, the spark will cease and the 
pilot flame-monitoring period will start.  The pilot 
flame-proving signal should be 2.5 - 5.0 µA. 
 
e) On completion of the pilot proving period, the 
green ’normal firing’ lamp will illuminate however, as 
the main gas solenoid valves have been 
disconnected, the controller will lockout after a 
maximum of 5 seconds.  The amber ‘lock-out’ lamp 
on the controller will be lit and the green ‘normal 
firing’ lamp will be extinguished. 
 
f) When the commissioning engineer is satisfied that 
the boiler has a stable pilot flame, switch off the boiler 
and re-connect the gas valve wiring plug assembly.

 

Содержание WESSEX-HE 200

Страница 1: ...BE READ AND UNDERSTOOD BEFORE INSTALLING COMMISSIONING OPERATING OR SERVICING EQUIPMENT WESSEX HE 200 WESSEX HE COUNTY HOT WATER BOILER FOR HEATING AND DOMESTIC HOT WATER INSTALLATIONS INSTALLATION CO...

Страница 2: ...ating safely and efficiently Maintenance Agreements 01202 662555 Regular routine servicing of equipment by Hamworthy service engineers inspects the safety and integrity of the plant reducing the risk...

Страница 3: ...PPLIANCE INSTALLED IN A SEPARATE BOILERHOUSE WITH ADEQUATE VENTILATION AND IS NOT CERTIFIED FOR USE IN DOMESTIC APPLICATIONS THIS BOILER IS FOR USE ON GROUP H NATURAL GAS 2ND FAMILY I2H AND LPG PROPAN...

Страница 4: ...SYSTEM 5 6 1 Suction 6 2 Design Waste Gas Volume and Temperature 6 3 Flue Condensation 6 4 Surface Temperature 6 5 Flue Pipe Location 7 0 AIR SUPPLY 6 7 1 Air Supply by Natural Ventilation 7 2 Air Su...

Страница 5: ...ernal Controls 2 Installation Noise 11 7 User s Instructions 12 0 FAULT FINDING 13 12 1 Summary of Safety Features 12 2 Fault Finding 12 3 Causes of Lockouts 13 0 SERVICING 14 14 0 REPLACEMENT OF FAIL...

Страница 6: ...HAMWORTHY HEATING LTD WESSEX HE 200 BOILER 500001008 K iv...

Страница 7: ...he Wessex HE has a low water content and water flow rates MUST be maintained at or above the mini mum levels shown in Section 8 and Fig 3 1 2 This boiler must be installed and serviced by a competent...

Страница 8: ...6 0 Water Content not including headers litres 20 40 System Design Flow Rate 11 C DT Rise l s 4 28 8 56 Minimum Flow Rate 15 C DT Rise l s 3 42 6 83 Shipping Weight kg 257 515 ELECTRICAL DATA Power Co...

Страница 9: ...treated to prevent precipitation of scale or sludge in the boiler water passageways Details of additives can be obtained from any reliable manufacturer of water treatment products or the local Water A...

Страница 10: ...Supply pipes must be fitted in accordance with BS 6891or UP 2 as appropriate Pipework from the meter to the boiler must be of adequate size Do not use pipes of a smaller size than the boiler gas conne...

Страница 11: ...the flue exceeds 4metres 6 2 Exhaust Gas Volume and Temperatures The volumes etc relating to Propane firing can be found in Appendix A It is recommended that the volume and temperature of the waste g...

Страница 12: ...ombustion and general ventilation in addition to that required for any other appliance 7 1 Air Supply by Natural Ventilation The purpose provided space housing the boiler must have or be provided with...

Страница 13: ...t connection A vent pipe and cold feed pipe must be fitted to the water system between the boiler and the first isolating valve in the water system The sizes of these pipes are shown below The vent pi...

Страница 14: ...water flow rate shown in Figure No 3 is maintained It is recommended that a water flow switch is fitted to the system The switch should be connected such that the boiler cannot fire unless the water f...

Страница 15: ...s for all boilers The method of connection to the mains electricity supply must facilitate complete electrical isolation of the boiler module with a contact separation of at least 3mm in all poles A m...

Страница 16: ...o connecting the boilers to the flue system Care must be taken to prevent damage to the casings prior to contract completion NOTE Fit the top insulation panel to the boiler prior to installing the flu...

Страница 17: ...ion 7 iii The system is fully charged with water ready to receive heat all necessary valves are open and the pump is running and circulating the water iv The pipework and valve arrangement is installe...

Страница 18: ...e test point and for reference CO2 measurements should be between 9 and 10 or 3 5 to 5 0 O2 Normal CO levels should not exceed 200 ppm NOTE All the above measurements refer to dry flue gas samples 11...

Страница 19: ...uit if fitted is made A 230 Volt supply on the Programmer Terminal No 1 will determine this c Check that the remote stop start circuit loop across terminals C5 and C6 is made Check Fascia mounted swit...

Страница 20: ...filter if fitted pressure gauge etc are in a serviceable and working condition and still comply with the relevant and aforementioned standards and Codes of Practice 13 2 1 Remove controls cover by un...

Страница 21: ...e differential pressure switch Bundy pipes to check that they are clear when they have been detached from the pressure switch to prevent damage to the diaphragm d Gently brush both sides of swirler lo...

Страница 22: ...system This is best carried out by specialists using suitable chemicals Follow the chemical manufacturer s recommendations and instructions regarding method solution strength and safety and handling...

Страница 23: ...recautions 13 4 9 Clean up mating surfaces and re assemble covers to tube plates with new gaskets lightly greased before assembly Torque the M12 bolts down evenly to 81Nm 13 4 10 a Re assemble baffles...

Страница 24: ...nd 5 pin Wieland plug fitted and that there is a replacement rubber gasket packed loose Un plug fan assembly from main controller wiring loom Remove the four M5 Pozidrive screws holding the controls b...

Страница 25: ...rked 3 COM c Green Yellow wire to earthing terminal Tighten cable gland Check switch is set to 1 2 mbar and replace cover plate Start the boiler several times to check for reliability 14 6 Control The...

Страница 26: ...eads to the appropriate item spade connectors Release switch or lamp from mounting fascia by pressing in the plastic retaining lugs at the top and bottom Pull components out frontwards Push in new com...

Страница 27: ...noid Valve 533903030 Pilot Solenoid Coil 533903031 Differential Pressure Switch 533901394 Control Thermostat Landis Gyr 339009345 IMIT 533901178 Temperature Limiter Landis Gyr 339011044 IMIT 533901179...

Страница 28: ...HAMWORTHY HEATING LTD WESSEX HE 200 BOILER 500001008 K 22 Figure No 2 Typical Boiler Installation...

Страница 29: ...HAMWORTHY HEATING LTD WESSEX HE 200 BOILER 500001008 K 23 Figure No 3 Wessex HE 200 Module Waterside Pressure Loss...

Страница 30: ...4 FN FN L N E 24 Figure No 4 Terminal and Mains Cable Layout KEY I BOILER CASING II CABLE CLAMP III SUGGESTED CABLE ROUTE IV CABLE GUIDE V TERMINAL BLOCK VI CONTROL THERMOSTAT VII WIRING DETAIL VIII E...

Страница 31: ...I Power ON Lamp Red II Temperature Limiter III Control Thermostat IV EMC Filter V 2A Fuse VI Sequence Controller inc Layout VII Gas Pressure Switch if fitted VIII Probe Test Link Terminal IX Flame Pro...

Страница 32: ...BOILER CASING III PROGRAMMER IV GAS VALVE WIRING PLUG V PILOT BURNER VI BY PASS GAS VALVE VII MAIN GAS VALVE VIII GAS ORIFICE IX Rp1 GAS CONNECTION X PRESSURE TEST POINTS XI DIFFERENTIAL PRESSURE SWIT...

Страница 33: ...nition Circuit Off Pilot Proving Period Starts YELLOW RED Position E Main Gas Valve opens RED YELLOW Position F Pilot Gas Valve Closes YELLOW GREEN Position G Burner Normal Run GREEN WHITE Position H...

Страница 34: ...HY HEATING LTD WESSEX HE 200 BOILER 500001008 K 28 1755 1190 400 600 377 BS 4504 PN6 80 DIA 344 I DIA 320 215 102 300 OUTLET 884 320 300 INLET Rp 1 GAS 540 22 DIA 640 Figure No 9 Boiler Dimensions Cle...

Страница 35: ...essex Pilot Burner Assembly Key I ELECTRODE PROBE SCREW 748132146 II SPARK ELECTRODE 333801440 III FLAME PROBE 533805006 IV JET CARRIER 333310871 V IGNITER BLOCK 333311465 VI PILOT INJECTOR 331101959...

Страница 36: ...HAMWORTHY HEATING LTD WESSEX HE 200 BOILER 500001008 K 30 BS 4504 PN6 80 DIA Rp 1 GAS 600 358 I DIA 775 711 775 221 775 141 1345 1031 45 Rc Rc Figure 11 Arrangement Drawing Wessex HE County...

Страница 37: ...al Gas is increased to 17 5mbar for Propane f Relevant labels are replaced to indicate the appropriate gas for which the boiler module is set up to fire The following tables paragraphs and figures usi...

Страница 38: ...r across the orifice NOTE The above is a first order check Final setting must be made using a gas meter 11 5 2 Combustion Checks A flue gas sampling point is provided in the front boiler casing see Fi...

Страница 39: ...OILER CASING III PROGRAMMER IV GAS VALVE WIRING PLUG V PILOT BURNER VI NOT USED VII MAIN GAS VALVES 2 OFF VIII GAS ORIFICE IX Rp1 GAS CONNECTION X PRESSURE TEST POINTS XI DIFFERENTIAL PRESSURE SWITCH...

Страница 40: ...o 8 Burner Flow System Schematic Propane KEY I Manual Gas Valve Ball Type II Control Gas Valves III Not Used IV Pilot Gas Valve V Pilot Burner VI Main Burner VII Differential Pressure Switch VIII Burn...

Страница 41: ...HAMWORTHY HEATING LTD WESSEX HE 200 BOILER 500001008 K 35 NOTES...

Страница 42: ...HAMWORTHY HEATING LTD WESSEX HE 200 BOILER 500001008 K 36 NOTES...

Страница 43: ...Notes...

Страница 44: ...y reserves the right to make changes and improvements which may necessitate alteration to the specification without prior notice Connect direct Direct Dial Telephone and Fax Numbers Direct Email Addre...

Отзывы: