HAMWORTHY HEATING LTD
31
SHERBORNE
500001167/E
10.2.2.2 SE71c
•
Isolate the boiler from the system & drain it down.
•
Disengage the appliance flue connector from the sump casting. Un-plug the condensate tube from the trap
•
On the SE71c Model remove the return (lower) connection & heat exchanger connecting pipe from the rear of
the boiler, secured by M8 nuts & washers. Note, there is an ‘O’ ring used on each fitting.
•
Support the sump & remove the 4xM6 securing nuts. Lower the sump to expose the heat exchanger & baffles.
•
To clean the heat exchanger(s), the use of a high pressure water hose (40-80 psi) is recommended with the
resultant discharge being collected in a suitable receptacle.
Primary Exchanger -
Insert cleaning nozzle into the burner opening. Switch on the pump & traverse the full
length & circumference of the heat exchanger to remove any deposits
Condensing Heat Exchanger -
Using the high pressure hose, traverse the exposed top & side of the heat
exchanger angling the sump to drain.
Should a high pressure hose not be available, the respective heat exchangers will have to be removed from the
casings. Each module holds approximately 4 - 5 litres of water & weighs 50 - 60kg (depending on model). It is
strongly recommended
that a minimum of two people are on hand to lift the module from the wall. Alternatively,
two lifting eyes are provided for use with suitable lifting equipment.
•
Place the module on two blocks of wood so the heat exchanger front casting is supported off the floor to
protect from damage.
•
Remove the 4xM10 nuts securing the front casting to the aluminium casing & carefully lift the casing vertically
upwards away from the heat exchanger.
•
Unhook the stainless steel springs & remove the 16 stainless steel baffle plates to expose the finned tubes.
•
Wire brush both sides of the baffles to remove any deposits.
•
Thoroughly wire brush the finned tubes.
10.2.3 Re-assembly
•
Re-assemble in reverse order & refit heat exchanger to the casing using a new gasket. Replace the water
connection gaskets on the rear of the boiler. Re-connect the water connections using new ‘O’ rings. Carefully
lift the module back onto the wall plate & secure with the M10 nut & bolt on the left hand side mounting. Re-fit
the system pipework & check for soundness.
•
Re-assemble the fan/transition/burner assembly using new gaskets where necessary, & refit in reverse
order.
Test all gas joints broken or disturbed for soundness before firing
. Re-light the boiler, check &
adjust the combustion as described in Section 7.
•
Check thermostat settings & adjust if required.
•
Re-fit the boiler cover & tidy floor around boiler as necessary.
Содержание Sherborne Series
Страница 2: ......
Страница 10: ...HAMWORTHY HEATING LTD 8 SHERBORNE 500001167 E 4 Boiler Layout Description 4 1 Accessory Pack...
Страница 27: ...HAMWORTHY HEATING LTD 25 SHERBORNE 500001167 E...
Страница 29: ...HAMWORTHY HEATING LTD 27 SHERBORNE 500001167 E 8 9 Wiring Diagram...
Страница 30: ...HAMWORTHY HEATING LTD 28 SHERBORNE 500001167 E 8 10 Wiring Diagram LMU...
Страница 39: ...HAMWORTHY HEATING LTD 37 SHERBORNE 500001167 E External Control Wiring for Multiple Module Installation...
Страница 53: ......
Страница 54: ......