background image

 

HAMWORTHY HEATING LTD 

 

17 

SHERBORNE 

 

500001167/E 

7.3 INITIAL LIGHTING 

 Only competent people registered for working on non-domestic gas appliances should attempt the following 
operations. Before commissioning a boiler ensure that all involved are aware of what action is about to be taken. 
 

• 

Record all readings for future reference on relevant commissioning sheet. 

• 

Allow system to warm up sufficiently to check operation of control thermostat. 

• 

A combustion check must be taken when first commissioning the boiler.  A sampling point is provided.  

• 

 

NOTE! Flue components can be hot enough to cause injury if touched when boiler is firing 
 

7.3.1 Lighting the boiler 

1. 

Ensure the boiler gas isolating valve is closed.  

2. 

Switch on the electrical supply  

3. 

Press the mode button to continuous operation (see section 8) 

4. 

The boiler will start-up & go through the ignition sequence. As the gas is isolated, the control will go to 
lockout as displayed on the display screen. Refer to section  8 of Controls Operation.  

5. 

If the above procedure occurs correctly, open the gas isolating valve. Reset the lockout & the fault 
indication will extinguish. 

6. 

The boiler will commence its ignition sequence as previously described. This time, when the gas valve is 
energised the burner will ignite. 

 
 
 
 
 
 
 
 

7.3.2 Safety Checks 

 

 To check for correct operation of the controller, with the boiler running, switch Off the gas supply at the isolating 
valve, the boiler should shutdown within one second & make a re-ignition attempt. As the gas is isolated, the 
control will go to lockout.  Switch On the isolating valve. Wait at least 15 seconds before pressing re-set button  on 
fascia to re-set controller.  After a waiting period the boiler will light & run normally. 
 

7.3.3 Flame Signal Assessment

 

 The flame ionisation signal generated whilst the boiler is firing, can be viewed directly from the display screen. 
The value should be approximately 15-20µA, but not less than 3µA.  
 

7.3.4 - Adjusting the settings of the boiler 
 

The desired Flow temperature setpoint can be set as follows.  
 
 With the boiler in normal operation

press the boiler temperature button & the current set-point will be displayed 

(factory set to a maximum flow temperature of 80°C). Pressing the 

or 

buttons will increase or decrease the 

setpoint in 0.5°C increments within the limits set in the program. 
After changing the setpoint to the desired value, the mode key must be pressed to store the value. 
Note: the screen will revert back to the Default Screen after a few seconds.  
 

7.4  Ignition Controller Check. 

  With the burner firing, the flame signal should be at least 3µA.  To check for correct operation of the ignition 
controller, close the gas valve. The boiler should shutdown after approximately one second & attempt a re-
ignition. Check that the flame has been extinguished 
 

7.5 Gas Supply Pressure Check. 

.When the boiler modules have been checked for correct operation the gas supply pressure should be checked. 
This should be done with all modules firing. 
 For Natural Gas the gas control valve zero governor control system is configured for a nominal gas inlet pressure 
of 20mbar measured at the rear of the boiler, with a maximum inlet pressure of 25mbar.

 

 

For LPG firing boilers, the nominal gas inlet pressure is 37mbar with a maximum inlet pressure of 45mbar. 

 

Mode button 

Содержание Sherborne SE64he

Страница 1: ...OPERATING OR SERVICING EQUIPMENT Sherborne Series Boilers Room Sealed Fully Modulating Pre Mix Gas Fired Boilers for Heating Domestic Hot Water Installations Installation Commissioning and Servicing...

Страница 2: ......

Страница 3: ...E ENSURE RELEVANT INFORMATION REQUIRED WITHIN DOCUMENT IS FOUND RELATING TO SPECIFIC GAS TO BE FIRED BEFORE FIRING BOILER THIS BOILER COMPLIES WITH ALL RELEVANT EUROPEAN DIRECTIVES EC TYPE CERTIFICATE...

Страница 4: ...d Systems 5 8 7 Sealed Systems 5 9 Electrical Connections 6 0 PRE COMMISIONING 15 6 1 Gas Supply 6 2 Ventilation 6 3 Pipework valves pump 6 4 Flue 6 5 Electrical 7 0 BOILER CHECKS 16 7 1 Boiler Gas Sy...

Страница 5: ...APPENDIX B ELECTRICAL CONNECTIONS CONTROLS 36 APPENDIX C FLUE DATA 38 C1 1 General Requirements C1 2 Waste Gas Volume Temperature C1 3 Materials C1 4 Suction C1 5 Disconnection C1 6 Flue Discharge C1...

Страница 6: ...e satisfied including interlocks which will shut the boiler s off should a high or low pressure fault occur Pressurisation units must also incorporate a low level water switch which protects the water...

Страница 7: ...separately from the boilers Ancillary items such as isolation valves flexible boiler connectors are packaged in a cardboard box on the same pallet The dimensions of these packages are shown below Deli...

Страница 8: ...Hole Gas 3 4 Electric M20 Electric M20 Cover removal clearance 30 Return 50 Flow 200 Flue 76 Flow 140 Flue 154 Return 185 460 280 600 A B 800 Water connections 85 200 320 Boiler Model Return connecti...

Страница 9: ...terials Also important is allowance for sufficient access at front sides top bottom of boiler for flue pipework connections A minimum space of 450mm in front of the boiler is required for removal of t...

Страница 10: ...HAMWORTHY HEATING LTD 8 SHERBORNE 500001167 E 4 Boiler Layout Description 4 1 Accessory Pack...

Страница 11: ...1 IGE UP 1A Gas installation must be purged to BS 6891 or IGE UP 1 IGE UP 1A Inlet gas pressure to boiler for Natural Gas should be nominal 20mbar minimum 17 5mbar dynamic at the connection to the bo...

Страница 12: ...suction is greater than 30Pa refer to HHL Technical This condition must then be checked hot and with all boilers firing the max pressure at the connection to the boiler should be 100Pa positive In th...

Страница 13: ...ECTIONS APPENDIX B 5 7 Mounting the boiler to the wall Select a position on the wall or the position the free standing frame with the minimum clearances from section 4 Position the template on the wal...

Страница 14: ...plate over the flue securing it to the wall Fit the flue support cradle over the end of the flue pipe Fit the flue concentric adaptor to the rear of the flue protruding into the boiler Ensure orienta...

Страница 15: ...lf supporting using wall brackets where necessary In terminating the flue ensure that the joint through the wall roof is made good weatherproofed Whilst carrying out the above procedure ensure that al...

Страница 16: ...end the use of the connection for the safety valve as detailed in Figure 3 2 Where HHL pipework kits are used their assembly instruction manual is supplied with the kit 5 9 Electrical Connections The...

Страница 17: ...to Hamworthy Heating recommendations Circulating system is full of water vented pressurised appropriately Circulation pump is fitted working interlocked where required Pipework connections to boiler a...

Страница 18: ...or normal operation The following checks must be made prior to lighting the boiler Check gas supply is connected but turned to off position Check unions fittings are correctly tightened test points cl...

Страница 19: ...h On the isolating valve Wait at least 15 seconds before pressing re set button on fascia to re set controller After a waiting period the boiler will light run normally 7 3 3 Flame Signal Assessment T...

Страница 20: ...ase the CO2 level turn the adjustment clockwise CO 0 50ppm However the figure must not exceed 200ppm under normal operating conditions If combustion readings fall within the required range the boiler...

Страница 21: ...safe reliable operation all wiring between sensors master slave boilers must be separated from mains voltage wiring 8 1 Fascia Details 8 2 Display Details In it s standard version the screen displays...

Страница 22: ...ss the information button to switch back to the information display or the mode button to return to the default display After 8 minutes the display will automatically change back to the default displa...

Страница 23: ...of the display 8 5 1 Internal Error Code Display If the fault cannot be rectified then extra information can be obtained from the internal error code To obtain this code press the into button then pr...

Страница 24: ...thermostat Investigate cause of overheating see section 9 3 113 Flue gas supervision equipment has cut out 117 Water pressure too high 118 Water pressure too low 119 Water pressure switch has cut out...

Страница 25: ...rameter to be set To leave the programming mode without changing the current parameter press the information button If no button is pressed for 8 minutes the screen will return to the default display...

Страница 26: ...y set Refer to section 8 3 2 for an explanation of how to set this Each time the or button is pressed during the time setting the seconds are set to 0 The clock continues to run while making the setti...

Страница 27: ...HAMWORTHY HEATING LTD 25 SHERBORNE 500001167 E...

Страница 28: ...ntrol Panel Assembly The control system is contained within the control panel pod on the side of the boiler The front panel can be re moved by removing the two screws at either side of the panel The f...

Страница 29: ...HAMWORTHY HEATING LTD 27 SHERBORNE 500001167 E 8 9 Wiring Diagram...

Страница 30: ...HAMWORTHY HEATING LTD 28 SHERBORNE 500001167 E 8 10 Wiring Diagram LMU...

Страница 31: ...to cool to normal operating temperature If after pushing the reset pushbutton resetting the lockout the code on the display does not extinguish the boiler does not fire up it is possible that the lim...

Страница 32: ...venturi tube with a soft brush if necessary Remove the 2 nuts securing the burner to the heat exchanger carefully remove the burner assembly Remove the single socket cap head screws securing the igni...

Страница 33: ...ly recommended that a minimum of two people are on hand to lift the module from the wall Alternatively two lifting eyes are provided for use with suitable lifting equipment Place the module on two blo...

Страница 34: ...ing the thermostat to the display panel withdraw the capillary bulb from the sensing pocket in the front of the heat exchanger Check the operation of the device by carefully applying a heat source to...

Страница 35: ...plugs are firmly correctly located Re light the boiler check adjust the combustion as detailed in Section 7 11 6 Main control PCB Part No 533901508 SE64he Nat Gas Part No 533901xzy SE71c Nat Gas Part...

Страница 36: ...PG 533901511 Fascia PCB 533901437 Fan assembly 533901376 Flow return Sensor 533901431 Flame sensing probe 533805019 Hot Surface Igniter 563801011 Temperature Limiter 533901179 Pressure Switch 53390149...

Страница 37: ...ximum Gas Inlet Pressure mbar 25 Minimum Gas Inlet Pressure mbar 12 5 Gas Flow Rate maximum m3 h Target CO2 at High Low fire 0 25 8 7 7 4 GENERAL DATA BOILER MODEL Model Sherborne SE64he Sherborne SE7...

Страница 38: ...n of the single boiler battery with a separation of at least 3mm in all poles 3 A mains isolator must be provided adjacent to the boiler in a readily accessible position The supply should only serve t...

Страница 39: ...HAMWORTHY HEATING LTD 37 SHERBORNE 500001167 E External Control Wiring for Multiple Module Installation...

Страница 40: ...high thermal efficiency of the boiler condensation in the flue will occur It is strongly recommended that twin wall or insulated flue pipe is used on all installations b Care should be taken to ensure...

Страница 41: ...lication requires the flue discharge to terminate below 2m above ground level the use of a terminal guard is required C1 7 Surface Temperatures Combustible materials in the vicinity of the boiler flue...

Страница 42: ...stable 100 150 x 1m long 029 030 Ref Concentric Flue Ref Concentric Flue Ref Horizontal terminal Assembly 100 150 031 Eccentric Adaptor Enlarged detail showing cut 80 100 80 Flue Support Bend 023 Ref...

Страница 43: ...Eccentric Adaptor Flue type C33 150 x 100 80 100 80 Flue Support Bend Ref 020 Ref 043 023 Ref Ref 001 Ref 029 Ref 030 Ref 033 027 Ref 028 Ref 038 Ref 044 Ref Ref 032 Flat Roof Flashing Adjustable Flas...

Страница 44: ...t 0 4m min 10m max Ref 023 Ref 001 80 Flue Support Bend Outlet 0 4m min 10m max 80 100 Outlet 10m max Inlet 1 0m max Single Flue Single Flue Single Flue 250 long 100 1000 long 100 500 long 100 Wall Cl...

Страница 45: ...ng 100 Single Flue Ref 026 Vertical terminal 100 Flue Ref 023 80 100 Eccentric Adaptor Ref 017 Wall Clamp 100 Ref 022 021 Ref 020 Ref Single Flue 500 long 100 1000 long 100 Single Flue Single Flue 250...

Страница 46: ...d in a boiler room or internal space the room or internal space must have permanent air vents directly to the outside air at high level at low level with the general requirements detailed above on loc...

Страница 47: ...mpartment ventilation is used Where grilles communicate directly with outside air they shall be positioned on the same wall Mechanical Ventilation Flow Rates Flow rate per kW total rated heat input Ne...

Страница 48: ...o ensure equal flow in each module or with a single pipe header system Figure E1 1 1 on the following page show typical layouts Ideally individual valves should be fitted to each module to enable isol...

Страница 49: ...tic Valve valve Drain Valve Module Hamworthy Modular Boilers Safety T valve Module 1 2 Drain 3 Module P gauges Pressure Temperature T Automatic Ai r Vent Heating lo ad Lockshield va lve fill line Temp...

Страница 50: ...w circuits during periods of low heat demand E1 10 Waterside Pressure Drop The waterside hydraulic resistance Pressure drop is given in table at beginning of Appendix E E1 11 Water Flow Controls Any e...

Страница 51: ...E 500001167 E Schematic for Single Boiler System Schematic for Single Boiler Primary Circuit System Schematic for Multiple Boiler External 0 10V Primary Circuit System Schematic for Multiple Boiler HH...

Страница 52: ...HAMWORTHY HEATING LTD 50 SHERBORNE 500001167 E INSTALLER SITE ADDRESS BOILER TYPE BOILER SIZE S UNIT NO S SERIAL NO S FLUE USEFUL USER INFORMATION NOTES...

Страница 53: ......

Страница 54: ......

Отзывы: