background image

4

2-Layer Film Install 

Revision date: 04.17.20

RIBBON BOARDS — CUSTOMER SUPPLIED (REQUIRED) — FOR ROLL-UP SIDE

Greenhouses equipped with roll-up side panels require a ribbon board. Materials for ribbon 

boards are 

not included

 and are 

supplied by customer

. Examples below show ribbon board as 

attached to frame. 

 

 

IMPORTANT:

 Installation of customer-supplied ribbon board is described later in this guide. 

Do 

not install boards at this time.

Required Lumber — Customer-Supplied — Ribbon Boards

RIBBON BOARD HEIGHT:

 Consult main frame 

technical document to determine ribbon board height 

for your greenhouse.

ATTENTION:

 Fasteners to secure boards to building frame are included with building materials. 

Minimum

 lumber dimensions shown; wider boards can be 

used if desired. Counter sink holes for 1/4" carriage bolts if bolt length is too short for selected board thickness.

Ribbon Board

 

Baseboard 

Actual frame may differ from example shown.

Diagram shows ribbon board attached 

for roll-up sides and film roof

NOTE:

 Flashing and u-channel are not shown.

RIBBON BOARD FOR ROLL-UP SIDES

1/4" x 3-1/2" (FAH008B) or 

1/4" x 4" (FAH009B) carriage 

bolts & 1/4" nuts (FALB01B).

Carriage bolt length depends 

on rafter pipe diameter.

Rafter

2" x 6" Board

Содержание PGFLSAXXFCW0063

Страница 1: ...ssion Photo may show a different but similar model Greenhouse with single door and roll up sides is shown in the example 2 Flashing Ribbon Board Baseboard 102197 U Channel Install Film Layer 1 Air Inf...

Страница 2: ...to prevent entrapment Important Information Contents Important Information 2 Required Lumber Customer Supplied Ribbon Boards 4 Recommended Customer Supplied Baseboards 5 End Panel Installation Detail...

Страница 3: ...ers for wire spring 1 4 or 5 16 drill bit 1 3 8 hole saw bit Hand tools saw or grinder to cut aluminum flashing Clamps to install u channel flashing Ladders work platforms and other machinery for lift...

Страница 4: ...sult main frame technical document to determine ribbon board height for your greenhouse ATTENTION Fasteners to secure boards to building frame are included with building materials Minimum lumber dimen...

Страница 5: ...oards run the frame length along both sides at ground level Installation of customer supplied baseboard is described later in this guide Do not install boards at this time ATTENTION Fasteners to secur...

Страница 6: ...r Apply foil tape DH8007 to cover all open cells after cutting and before flashing if this has not been completed yet U channel flashing overlaps end panels to cover open cells at top If end panels ar...

Страница 7: ...re rafter begins to bend Place flashing on ground or work bench 3 From first cut mark remainder of flashing face at 12 on center intervals Flashing PGFLSAXXFCW0063 Installation ATTENTION To bend flash...

Страница 8: ...ed Use hand clamps to help hold and bend flashing into position 9 Continue installing flashing and work down to ground INSTALL FLASHING CONTINUED Flashing 6 7 Flashing ATTENTION Be mindful of where to...

Страница 9: ...frame are included See ribbon board information earlier in this guide Complete these steps 1 Using diagrams included in frame assembly Guide 1 mark ribbon board location on frame along each side at e...

Страница 10: ...nuts Review diagram below INSTALL RIBBON BOARDS 1 After flashing is installed attach ribbon boards to assembled frame Use a drill and 5 16 drill bit to drill through rafter tubes and ribbon board Secu...

Страница 11: ...u channel using FA4482B Tek screws NOTE Align u channel with center of end rafter and install over and through the installed flashing 2 Continue to install u channel up and over the end rafter down to...

Страница 12: ...wood screws 2 Continue attaching u channel and work toward other end of frame U channel to run level throughout installation 3 Cut last section to required length so it is flush with outside edge of...

Страница 13: ...rn to rafters and apply tape over connectors to better protect cover film and prolong film life once installed Photo above shows one way to apply the tape Rafter and frame shown above may differ from...

Страница 14: ...to prevent serious personal injury DO NOT attempt to install the main cover on windy or stormy days WEAR EYE PROTECTION WHEN INSTALLING SPRING WIRE DOUBLE LAYER FILM INSTALLATION Greenhouses equipped...

Страница 15: ...nger than required to cover frame end to end For easier anchoring allow approximately 10 to extend past end rafter as film is anchored Remove ropes if used after film is secure 6 Continue down both ed...

Страница 16: ...the side Use upper run of u channel to secure roof film if two 2 runs of channel are attached to ribbon board 10 Next move to remaining side stretch film and secure in place Pull film sung during spri...

Страница 17: ...the example Some larger buildings may include multiple inflation fan kits ATTENTION Install all air inflation fan kit components before installing the second layer of film Failure to do so will requir...

Страница 18: ...Lower run of u channel is reserved for roll up side panel ATTENTION Install second layer of film with either surface toward the soil Do not damage first film layer during installation of second film 2...

Страница 19: ...Greenhouse Anytime after roof film installation apply sealant to these areas Around all doors Around accessory framing and accessories At joint where u channel meets flashing for both end rafters All...

Отзывы: