 ROUND PREMIUM EXTRA TALL HIGH TUNNELS

LAY OUT THE BUILDING SITE

After the site is prepared, lay out the building site.

Taking these steps 

before

 assembling the shelter saves 

time and ensures that the structure is positioned as 

desired. 

Ground posts must be driven to the proper depth. Width of 

the shelter is measured from the center of one ground post 

to the center of the remaining ground post.

SQUARE THE SITE

Gather the parts:
•  Ground posts
•  5/16" x 2-1/2" machine bolts 
•  5/16" nuts
1.  Identify a corner where a ground post will be positioned 

and drive the first ground post into the ground.  

 

NOTE: 

Insert the ground post driver into the top of 

the ground post to protect the post and drive the post 

into the ground. 

The top of the post will be one (1) foot 

above the finished grade when properly driven.

 

4.  String a line at least as long as the building from the 

first stake at 90°. 

 

NOTE:

 A transit can be used to ensure an accurate 90°  

angle, or the 3-4-5 rule can be used. Refer to diagram.  

Using multiples of 3-4-5 such as 6-8-10 or 12-16-20  

helps to maintain an accurate 90° angle.

5.  After squaring the position of the building, measure the 

length and drive the next corner ground post.

6.  Repeat the same step for the last corner post. 

 

NOTE:

 The distance measured diagonally between 

corner posts must be equal for the building to be 

square.

7.  Check all dimensions (and adjust if needed) before 

driving the remaining posts to the required height.

8.  After all corner posts are accurately installed, tie a 

string line between the tops of the corner ground posts 

on the same side of the shelter. The string is used to 

identify the tops of all remaining ground posts. The 

string must remain tight and level.

9.  Use a tape measure to mark the 48" on-center 

locations of the remaining ground posts.

10. Drive the remaining ground posts into the ground at the 

required 48" on-center width and the height identified 

by the string. 

 

NOTE:

 Verify that the holes in the ground posts are in 

the proper position and that each post is plumb and 

driven to the correct depth.

ATTENTION:

 Position the pre-drilled holes facing to the 

inside/outside of the shelter so they can be aligned with 

the bolt holes in the rafter legs. 

 

To align the bolt holes in the ground posts with those 

in the rafter 

after driving the ground posts,

 insert a 

tapered rod or pry bar into a ground post bolt hole and 

turn the post using the rod or pry bar.

2.  After the first corner ground post is in place, string a 

line the width of the building (center-to-center) and 

drive the second ground post into the ground just 

enough to hold it in place.

3.  Use a transit or line level to drive the second corner 

post to the same depth as the first ground post.

Outside of 

Shelter

Inside of 

Shelter

Ground 

Post

Содержание PB01752R6

Страница 1: ...EXTRA TALL HIGH TUNNELS Photo may show a different but similar model STK DIMENSIONS PB01752R6 42 W x 15 H x 72 L 2020 GrowSpan All Rights Reserved Reproduction is prohibited without permission GrowSpa...

Страница 2: ...ing shoring and support needed during the assembly process For safety reasons those who are not familiar with recognized construction methods and techniques must seek the help of a qualified contracto...

Страница 3: ...if equipped This applies to fabric covers that stretch over the frame assembly Your shelter may include roof panels or side panels or both 11 Read the Care and Maintenance information at the end of th...

Страница 4: ...with roll up sides Materials for baseboards and ribbon boards are not included and are supplied by customer ATTENTION Fasteners to secure boards to frame are included Recommended lumber dimensions sh...

Страница 5: ...12 CC6214 Fabric Clips FA4482B Tek Screw 102857 End Clamp 102547 Cross Connector Swaged Plain Swaged and Plain Rafter Sections some pieces are not shown 102569 Bearing 102717 Gearbox Drive 102198 U Ch...

Страница 6: ...ng the end clamps cross connectors and purlins Ground Post Round Premium Extra Tall High Tunnel OVERVIEW This section describes assembling your high tunnel For additional details see section Assemblin...

Страница 7: ...d diagonally between corner posts must be equal for the building to be square 7 Check all dimensions and adjust if needed before driving the remaining posts to the required height 8 After all corner p...

Страница 8: ...ation purposes only 12 Verify that the on center width of the frame is uniform between the corner ground posts 6 on center 21 on center 21 on center 6 on center NOTE The frame is square when the two d...

Страница 9: ...es as shown below NOTE Band clamps QH1404 are only attached to two 2 interior rafter assemblies Use a piece of duct tape if desired to keep each clamp from sliding when the rafter is lifted into posit...

Страница 10: ...ew of the end rafter and clamps as shown from the outside when the frame is assembled 3 With the rafter pipes seated at each joint and the rafter positioned on a flat surface secure each joint with a...

Страница 11: ...mark the distance on the pipe NOTE This first measurement is three quarters 3 4 of an inch longer than the on center rafter spacing to account for the length of purlin pipe that extends through the e...

Страница 12: ...port is anchored to the ground post secure it to the socket fitting at the top of the rafter using an Allen wrench and the set screw DO NOT SECURE THE SOCKET FITTING TO THE RAFTER AT THIS TIME End Raf...

Страница 13: ...AUTION To prevent cover damage the ends of the purlins should not extend past the end clamp The bolt side of the end clamps must go toward the inside of the shelter the same side as the purlin as show...

Страница 14: ...er with a Tek screw 5 Check each purlin joint and secure using a Tek screw if this has not been done 20 Slide the center support into the center pocket of the end panel Be sure to position the drilled...

Страница 15: ...round posts using the 5 16 x 3 lag bolts Insert the lag bolts from the inside of the shelter through the ground posts into the baseboards Continue adding baseboards to complete the first run Splices a...

Страница 16: ...f a cable section and wrap the cable around the thimble as shown in the second figure to the right 4 Grasp both sections of the cable near the thimble and position one cable clamp one inch away from t...

Страница 17: ...me B A QH1404 Band Clamp CABLE PLACEMENT The diagram and inserts below identify the placement and proper way to attach the cable assemblies to the building 1 Attach the first cable assembly at the bot...

Страница 18: ...mage do not install end panels on a windy day Gather the parts Fabric clips CC6214 divide quantity in half Measuring tape Scissors Assembly Procedure 1 With the proper lift or ladders positioned insid...

Страница 19: ...he fabric clips as you work down from the top of the rafter Fabric clips are installed on the backside of the rafter to prevent damage to the main cover when it is installed 7 Verify that the end pane...

Страница 20: ...uble and single poly latch U Channel and poly latch springs 8 Install roll up side kits the anti billow ropes and test the operation of the twist of the wrist assembly INSTALL POLY LATCH U CHANNEL Att...

Страница 21: ...he single poly latch U channel 3 Repeat the steps to install the single U Channel at the remaining end of the frame 4 Continue with the installation of the main cover Single U channel Diagram may not...

Страница 22: ...at one end of the U Channel and work toward the other It is also possible to begin at the middle of each side and work toward each end NOTE Maintain an even length along the side The final stretching...

Страница 23: ...U Channel to the remaining area on the top of end rafters See diagram below U Channel Ribbon Board 15 Place and center a side roll up panel along one side of the frame 16 Attach side roll up panel to...

Страница 24: ...ach pipe into the plain end of another pipe until the conduit is assembled 3 Secure each pipe joint with a Tek screw 4 After assembling both conduits place one 1 conduit assembly at the base of each s...

Страница 25: ...hannel along the rafter at the end of the building where the Twist of the Wrist assembly will be located 5 Secure the upper end of the channel by drilling a 3 8 hole through the end rafter and attach...

Страница 26: ...rom the ground end This is the free end of the channel 13 Finish rolling the cover conduit in a clockwise motion up to the Twist of the Wrist assembly 14 Attach the conduit to the square shaft of the...

Страница 27: ...ditional parts if needed 3 Move up the same end rafter and drill a 3 8 hole through the poly latch U Channel and rafter leg insert an eyebolt through the hole and secure the eyebolt with a nut and was...

Страница 28: ...e debris and objects that may accumulate on the cover Use tools that will not damage the cover when removing debris Remove snow to prevent excess accumulation Use tools that will not damage the cover...

Страница 29: ...date 01 01 20 GROWSPAN ROUND PREMIUM EXTRA TALL HIGH TUNNELS Sidewall Height 42 0 3 10 9 16 15 0 Height F FR RO ON NT T Grid Represents 12 Squares QUICK START GUIDE 42 Wide Round Premium Extra Tall H...

Страница 30: ...GROWSPAN ROUND PREMIUM EXTRA TALL HIGH TUNNELS FRONT PROFILE 102676 102676 End 102857 Middle 102547 End 102857 Middle 102547 42R1902 10016108 42R1901D 102676 42R1901D 42R1902 42R1902 42R1902 42R1902...

Страница 31: ...31 Revision date 01 01 20 GROWSPAN ROUND PREMIUM EXTRA TALL HIGH TUNNELS SIDE PROFILE 11 131S075 1 131P0735 Purlin Run 6 0 Rafter Spacing On Center 72 0 Length Center to Center...

Страница 32: ...32 Revision date 01 01 20 GROWSPAN ROUND PREMIUM EXTRA TALL HIGH TUNNELS CONNECTIONS End Rafter Purlin Connection View 1 Mid Rafter Purlin Connection View 2 Rafter Strut Connection View 3...

Страница 33: ...PAN ROUND PREMIUM EXTRA TALL HIGH TUNNELS CONNECTION DETAILS 102547 Rafter View 2 Mid Rafter Purlin Connection Purlin Rafter 102857 View 1 End Rafter Purlin Connection Purlin View 2 Mid Rafter Purlin...

Отзывы: