INSTALL ROLL-UP SIDES
Complete the following steps:
1. Locate a roll-up side panel (DD) and roll it out along side of the
frame. Position panel pocket away from frame. See diagram
below.
2. Stretch roll-up panel and center it from end-to-end.
3. With assistance, lift panel (no pocket) edge up to lower run of
u-channel attached to ribbon board. Secure it in the channel
using 102198A u-channel spring.
NOTE:
Begin at one end of u-channel and work toward the
U-Channel
U-Channel
Upper channel
for main cover
Lower channel
for roll-up side
other. Verify the panel is centered on the frame. Side panels are longer than the frame. Trim to the desired length
after installing the twist-of-the-wrist components. Install panel evenly in the u-channel.
4. With top edge secured, spread free/loose edge of panel (with pocket) out so it hangs down evenly from u-channel.
NOTE:
Excess panel is rolled onto roll-up conduit during next procedure.
5. Continue with the following roll-up procedures to finish the installation.
Install Roll-Up Side Components