Open out flysheet and position in required direction 

 

Secure in position by zipping the awning onto the corresponding zip at the front of the tent 

 

Locate inflation points on each beam 

 

Remove the valve cap (figure 1) 

 

Insert the correct pump adaptor, which will lock onto the valve (figure 2 & 3) 

 

There is no need to turn the white valve button as the adaptor will move this to the correct position 

 

Inflate all tubes to 7psi. The tubes MUST be guided into an arch as they are inflated (figure 4) 

 

Final tube pressure MUST NOT exceed 8psi 

 

DO NOT OVER-INFLATE THE BEAMS 

 

Start with the center tube and guide the beam into an upright position while it is inflating 

 

Inflate the other beams. 

 

A small amount of air may leak from the valve when it is being inflated but this is normal 

 

Remove the pump adaptor as soon as the beam is at the correct psi 

 

Replace the valve cap to create an air tight seal (figure 5 & 6) 

 

Position the open end of the awning toward the tent 

 

Peg out awning base at contact point with the tent and then the front of the awning to tension the material 

 

Secure in position by pulling the guylines attached to the awning roof over the roof of the tent and pegging. 

 

Peg out the remaining poles and pegging points using pin pegs at the base of poles 

 

Peg out ALL guy lines using pin-pegs ensuring that guy line fabric attachment points are evenly tensioned.  

 

Reposition and adjust tensioning where necessary 

CORRECT PUMP SET-UP: 

 

Pump Body > Pressure Valve > Pressure Gauge > Hose 

 

(Ensure the valve/gauge/hose are connected to the inflation port of the pump) 

In the unlikely event of a puncture: 

 

Deflate the air beam. Unzip the internal flysheet sleeve which contains the affected beam. 

 

Remove the tube and its protective outer. 

 

The zips for the protective outer are cable tied together to prevent accidental access. Cut the cable tie and open the zip.  

 

DO NOT open these zips when the tube inflated. 

 

Remove the clear rubberised tube from the protective sleeve taking care when removing the valve from the sleeve. 

 

Partially inflate the tube and pass through a bucket or basin of water, looking for air bubbles. This will indicate location of puncture 

 

Use the repair patch provided and cover hole, using instructions on patch. Re-insert tube into protective outer, closing zip from both ends, so that zip 
pullers are in the flysheet sleeve (this might be easier with the tube partially inflated) 

TO DEFLATE  AIRBEAM/ AIRAWAY/ AIRAWNING:  

 

To deflate the AirBeam (remove the cap (figure 7)) press & turn (figure 8) the button from CLOSED to OPEN 
 

AIRBEAM INFLATION:

 

     

 

 

 

 

 

 

 

 

AIRBEAM DEFLATION: 

 

 
 
 
 
 
 

 

Figure 1 

Remove 

locking cap 

Figure 3 

Lock locking pump 
connector 

Figure 4 

Inflate with 
AirBeam pump 

Figure 5 

Insert locking 

cap 

Figure 6 

Lock locking cap 

Figure 8 

Push button to deflate & 

twist to open position 

Figure 7 

Unlock 
locking cap 

Figure 2 