5 INSTALLATION
It is essential that correct licenses are held to install and connect the panel to the Thermodynamic Box. All
personnel carrying out installation, maintenance or servicing of stationary refrigeration, air-conditioning or
heat pump equipment that contains or is designed to contain F-Gas refrigerants must hold the relevant
designated qualifications stated in the Australian Standards guidelines.
The plumbing work must be carried out by a plumber who is qualified to Level 3. Where necessary the
plumber must hold an Unvented Hot Water Certificate recognized by Competent Person Schemes (CPS)
approved to offer self-certification under Approved Document G.
Inside Australia the installation needs to be carried out in accordance with the country’s local regulations.
Installation Steps:
1. Install the Thermodynamic Box
2. Install the Thermodynamic Panel
3. Refrigeration connections
4. The sight glass
5. Hydraulic connections
6. Temperature Sensor
7. Electrical connections
8. Pressure test during the installation with nitrogen
9. Vacuum test during installation
10. Filling of the refrigerant circuit
11. Draining & bleeding of the hydraulic circuit
12. Temperature reduction valve
13. Turning the system on
5.1 INSTALLING THE THERMODYANAMIC BOX
Siting location
•
Make sure the fixing points and fixing methods will take the weight of the
Thermodynamic Box. Please refer the Fig.2 for the fixing location of the unit.
•
The Thermodynamic Box must be installed in horizontal position.
•
The equipment shall not be installed in a place where it exposed to corrosive gases, major electrical
fluctuations, high electromagnetic field, inflammable materials or other hazardous areas.
•
Minimum pipe diameter of 22mm should be used in the hydraulic system between the
Thermodynamic Box and water cylinder.