ERV+DX coil
23
a. b. c.
9) Keep the drain pipe downward with an inclination of 1°
~
2° or more.
Therefore, install a supporter every 1000-1500mm.
10) Make sure the weight of drain pipes won’t be borne by the unit.
3.4.3 Drainage Test
After completing the installation of the entire drainage pipeline (without
insulation cotton), perform a drainage test.
(1) The method of adding certain quantity of water to the water tray of the unit is as
follow:
1) Open the side panel of the unit, as shown below. Use hose to infuse 1.5~2L
of water to the water tray of the unit to observe if there’s leakage of drainage
system. The guide hose shall be inserted to the bottom of water tray for
watering operation. When infusing water, please observe if water flows out
from the drain pipe normally and make sure no water leakage in the
connection location of pipeline.