GNB Flooded Classic series Скачать руководство пользователя страница 16

13

tion of a fixed direct current (DC) through the external cell 

connections.  Some precautions must be observed to get 

consistent and meaningful values, however, and these are 

described in Section 19.3.

Resistance measurements or microhm measurements 

should be taken at the time of the installation and annually 

thereafter.  Initial measurements at installation become the 

benchmark values and should be recorded for future moni-

toring of electrical integrity.

Specific values of connection resistance vary with cell type, 

quantity of connectors, etc.  It is important that the bench-

mark value for all similar connections should be no greater 

than 10% or 5 microhms, whichever is greater, above the 

average resistance of all such connections in the battery.  If 

any connection resistance exceed the average by more than 

10% or 5 microhms, whichever is greater, the connection 

should be remade so that an acceptable benchmark value is 

established.  Benchmark values for connection resistances 

should also be established for terminal plates, where used, 

as well as cable connections.  Benchmark values should 

preferably be established upon installation. However, if that 

was not done, they may be established later provided the 

special procedure described below is followed.

Disconnect the battery from the charger and load and disas-

semble at least three (3) of the intercell connections.  Clean, 

neutralize and burnish these connection components as 

though they had corrosion (See Section 19.0) Reassemble 

each connection per Section  7.7 and determine its resis-

tance.  Measure the resistance of all similar connections in 

the battery.  If any connection resistance exceeds the aver-

age of the three remade connections by 10% or 5 microhms, 

whichever is greater, that connection should be remade to 

establish an acceptable benchmark value.

All benchmark values should be recorded.  Annually, all con-

nection resistances should be remeasured.  Any connection 

which has a resistance value more than 20% above the 

benchmark value should be corrected.

Increase in connection resistance of more than 20% above 

the  recorded  benchmark  definitely  indicates  a  degrading 

connection.  Such degradation may be caused by corro-

sion (See Section 19.0) or by relaxation in hardware torque 

value.  If there is no sign of corrosion, the higher resistance 

at the connection may be corrected by retorquing (See 

Section19.2).  If connection resistance is reduced to within 

20% of the benchmark value, no further action will be nec-

essary.  Failure to restore resistance to an acceptable value 

will necessitate reworking the connection.

Maintaining electrical integrity of connections is important as 

poor connection will result in reduced battery output and in 

extreme cases may cause melted cell posts, circuit interrup-

tions or battery fires.

19.2  Retorquing Connections

Retorquing of connections should be performed annual-

ly (See Section 9, 14) and when connection resistances 

have increased to more than 20% over the benchmark. 

Retorquing should not be done if visual inspection shows 

evidence of corrosion.  Retorquing when corrosion is present 

only restores mechanical compression but will not improve 

electrical integrity.

Tests reveal that a reduction in the original torque value of 

30% still provides a functional electrical connection if there 

is no corrosion between contact surfaces.

Retorquing of connections should always be to the recom-

mended value (See Section 7.7).

19.3  Connection Resistance 

 Measurements

Connection resistances are very small, usually in microhms.  

Therefore, precautions must be observed so that the mea-

sured values are meaningful and not misleading.  Different 

connector hook-ups require that the measurement technique 

allows for these differences.

 

 (i) 

Parallel Connector Hook-Ups. 

  

(Figure 6)

  

 

 

Parallel paths exist in this hook-up and measure- 

ment of connection resistance include all four con- 

nector post interfaces.  The location of probe points 

is not critical here because of the existence of par-

allel paths. An increase (decrease) in the lead mass 

between post and connector interface on one side 

is cancelled by an equal decrease (increase) in the 

mass on the opposite side.

 (ii) 

Four Post, Four Connector In-Line Hook-Ups.

  

(Figure 7)

 

 

Cells with four post connector hook ups require two 

measurements to monitor all eight post-connector 

interfaces.  Measurement is made in two steps— 

First between points A and C and then between 

points B and D.  The measured values should be the 

same. Values appreciably different (5 micrhoms or 

more) require reworking of connections as described 

in Section 19.0.

 (v) 

Four Post, Connector Parallel Hook-Ups.

 

    (Figure 8)

 
      

Cells arranged end-to-end have parallel current 

paths above and below the cell covers and require 

that resistance measurement make allowance for 

the same.  The current paths above the cover are 

provided by the connectors and the path under the 

cover is provided by the busbars (shown by dotted 

lines in Figure 10).  Most resistance meters apply 10 

amperes DC to the connections being monitored.  If 

this was done between posts A and B in Figure 10, 

the current will divide through the busbars between 

CAUTION!

TOO FREQUENT RETORQUING OF 

CONNECTIONS IS NOT RECOMMENDED AS 

THIS WILL RESULT IN DISTORTION OF CELL 

POSTS, CONNECTORS, ETC., THUS

 DEGRADING

 

RATHER THAN IMPROVING THE CONNECTIONS.

Содержание Flooded Classic series

Страница 1: ... INSTALLATION OPERATING INSTRUCTIONS SECTION 93 10 2016 07 A Division of Exide Technologies ...

Страница 2: ...YOUR GNB REPRESENTATIVE SALESPERSON TELEPHONE LOCATION GNB SERVICE ASSISTANCE 1 800 241 4895 ...

Страница 3: ... 10 3 Equalizing Individual Cells 9 10 4 Equalizing Charge Electrolyte Levels 9 SECTION 11 11 0 Specific Gravity 9 11 1 Hydrometer Readings 9 11 2 Correction for Temperature 10 11 3 Correction for Electrolyte Level 10 11 4 Specific Gravity Range 10 INDEX Page SECTION 12 12 0 Cell Voltage Variation 10 12 1 Cell Voltage Variation Damp Covers 10 12 2 Cell Voltage Temperature Correction 10 12 3 Correc...

Страница 4: ... installing cells Use a baking soda water solution 1 lb per gallon of water to prevent possible injury to personnel H Make sure that all battery connections are properly prepared and tightened to prevent possible injury to personnel or failure of system I Familiarize personnel with battery installation charging and maintenance procedures Restrict access to battery area permitting trained personnel...

Страница 5: ...me of the receipt it is recommended that it be stored indoors in a cool 60 F 15 6 C to 90 F 32 C clean dry location Do not top load pallets or possible cell damage may occur Storage or transport of flood ed lead acid batteries at temperatures exceeding 120 F 49 C can cause detimental effects on plastic components and battery state of health which may void warranty 4 2 Parts and Accessories Prior t...

Страница 6: ...n reduced life Therefore for longer life and ease of main tenance locations having cooler ambient temperatures are recommended The normal battery operating temperatures are between 60 F 16 C and 90 F 32 C 7 3 Temperature Variation The location of rack arrangement should result in no greater than 5 F 2 78 C variation in cell temperatures in a series string at any given time If a greater variation i...

Страница 7: ...be removed exposing copper As contact surfaces of posts and connectors are cleaned apply a thin coating of NO OX ID grease or approved equal to these surfaces only Starting at center of the cell row install connectors per wir ing diagram and cell arrangement drawing furnished with the battery On cells using stainless steel bolts washers and nuts make sure a washer is placed between the bolt head a...

Страница 8: ...5 ...

Страница 9: ...e diagonal corners of the cell These permit the taking of specific gravity readings at a point about one third from the top of the plates See Section 11 1 Refer to Figure 3 A flexible shipping cap and shipping plug is installed on each withdrawal tube The cap may be removed and dis carded after neutralizing or left in place as dust covers The red plug should be discarded Plastic Numerals See Page ...

Страница 10: ...48 36 55 2 50 32 44 8 2 Initial Charge Electrolyte Levels During the initial charge there will be an increase in the electrolyte levels and they may go above the high level mark See Section 3 2 This is due to gases that were lost during transportation or standing in storage being restored to the cells Do not remove any electrolyte even though levels may be above high level When battery is placed o...

Страница 11: ... voltage used Non uniformity of cells may result from low floating voltage due to improper adjustment of the charger or a panel volt meter which reads incorrect higher output voltage Also variations in cell temperatures greater than 5 F 2 78 C in the series string at a given time due to environmental con ditions or rack arrangement can cause low cells 10 1 Equalizing Frequency A Equalize when the ...

Страница 12: ...ecific gravity is used in determining a cell s state of charge It decreases as the cell discharges and increases as the cell is charged reaching its original value when the cell is fully charged Specific gravity is expressed to the third decimal place 1 215 and is measured by a hydrometer float enclosed in a glass barrel rubber bulb syringe Draw sufficient electrolyte into the barrels holding the ...

Страница 13: ...factory SECTION 12 12 0 Cell Voltage Variation The tabulation on the following page indicates the normal cell voltage variation that may exist with the battery on float and no greater than a 5 F 2 78 C variation in cell temperature NORMAL VOLTAGE RANGE Average Type Float Voltage Variation Lead Calcium Nominal 1 215 sp gr 2 17 to 2 25 V P C 0 05 V P C Nominal 1 250 sp gr 2 23 to 2 33 V P C 0 05 V P...

Страница 14: ...sistances of each cell to cell cell to terminal inter level and load connections Remake any connections that are more than 20 above installation base value Check integrity of the rack E Any time the battery is given an equalizing charge see Section 10 1 an additional set of individual cell readings should be taken after battery has been returned to nor mal float for one week These will serve as an...

Страница 15: ...lution 1 lb of bak ing soda per gallon of water DO NOT USE AMMONIA SODIUM HYDROXIDE OR ANY STRONG ALKALIES SECTION 19 19 0 Connections Battery terminal connections should be corrosion free and tight to provide satisfactory operation while supplying emer gency power and when on floating charging Visual moni toring of all connections should be made quarterly When corrosion is observed on any connect...

Страница 16: ...essitate reworking the connection Maintaining electrical integrity of connections is important as poor connection will result in reduced battery output and in extreme cases may cause melted cell posts circuit interrup tions or battery fires 19 2 Retorquing Connections Retorquing of connections should be performed annual ly See Section 9 14 and when connection resistances have increased to more tha...

Страница 17: ...t connector interfaces A better and preferred technique is to apply the 10 amperes DC to posts A and D such that equal current paths are provided Then the differences in readings across AB and CD will reflect connector interface problems in either of the two external intercell connections Both intercell connections should be reworked as described in Section 19 0 14 FIGURE 6 PARALLEL CONNECTOR HOOK...

Страница 18: ...15 GB 1000F A Division of Exide Technologies A Division of Exide Technologies A Division of Exide Technologies GNB Industrial Power ...

Страница 19: ...king strip They are easily removed by peeling back the plas tic strip Keep finger contact with adhesive backing on numeral to a minimum 5 Locate and place numeral on side of jar being careful that there is no conflict with electrolyte level lines or side rails of SEISMIC TYPE RACKS For clean appearance exercise care in numeral placement so that all the numerals are in the same relative position on...

Страница 20: ...opera tions in more than 80 countries in sales and service GNB Industrial Power is best positioned to satisfy your back up power needs locally as well as all over the world Based on over 100 years of technological innovation the Network Power group leads the industry with the most recognized global brands such as ABSOLYTE GNB FLOODED CLASSIC MARATHON RELAY GEL SONNENSCHEIN and SPRINTER They have c...

Отзывы: