Air-to-water heat pump 4 - 6 kW
English
Step 3: Evacuation
Connect the vacuum pump on the maintenance valve (with
Schrader). Run the vacuum pump until the relevant vacuum is
reached. Close the vacuum pump and start filling immediately.
The duration of the pumping empty process varies with differ-
ent lengths of the pipework and the pump output. The follow-
ing table shows the time required for pumping empty.
Step 4: Filling
Once the leakage tightness test and evacuation have been car-
ried out correctly, open the maintenance valves on the indoor
unit. For refrigerant lines > 7.0 m, top up the refrigerant accord-
ingly.
The heat pump is now ready for use.
Time required for pumping empty with a
0.1 m_/hr. Vacuum pump
Length of the pipework
less than 10 m
30 min. or longer
0.6 mbar or less
Содержание 041HOIAOW2
Страница 2: ......
Страница 37: ...www gdts one DOK41 HOIAO WxDEN FD 9912 35 Air to water heat pump 4 6 kW English...
Страница 38: ...36 DOK41 HOIAO WxDEN FD 9912 www gdts one English Air to water heat pump 4 6 kW...
Страница 39: ...www gdts one DOK41 HOIAO WxDEN FD 9912 37 Air to water heat pump 4 6 kW English...