39
4.2
LIVE STRAINER & CONTROL SYSTEM FLUSHING
It is recommended to flush the control system of the valve whenever possible to remove debris. This
procedure can be performed while the valve is live (i.e. still in service) but it is recommended that the
downstream system is isolated (i.e. downstream gate valve closed).
a. Depressurised control system as per section 4.1.
b. Ensure BV1, BV2 and CS isolation valves are all closed.
c. Remove and clean the strainer by unscrewing the hex plug.
d. Flush the control system with water by slowly opening, one at a time, BV1 & BV2.
Содержание NeoFlow DN200
Страница 1: ...Operating instructions NeoFlow Pressure Reducing Valve DN200 DN300...
Страница 10: ...10 1 7 BILL OF MATERIALS PRESSURE REDUCING ASSEMBLY...
Страница 12: ...12 1 8 BILL OF MATERIALS VALVE BODY...
Страница 23: ...23 2 2 2 PERMITTED VALVE ORIENTATIONS Horizontal Orientation Vertical Orientation...
Страница 42: ...42...
Страница 53: ...53 NeoFlow Diagnostic Flow Chart A...
Страница 54: ...54 NeoFlow Diagnostic Flow Chart B...