LFP Battery Module – Product Manual
All rights reserved genZ 2020
Issued for Use
Revision
Page
4/03/2020
2.1
8 of 25
6.5
Installation of a single Battery Module
Ensure that the following is considered prior to installing:
Use only genuine Anderson SB50 connectors.
Use the matching colour of Anderson SB50 connector as these connectors are keyed and (for
Example) only a blue Anderson will connect with a blue Anderson.
That the polarity of the connector is observed. + and – symbols are clearly marked on both
the connectors and the front panel of the module.
The correct size of cable to the battery connector is used.
6.6
Parallel Connection
In addition to the guidelines for a single module, when connecting in parallel, the following additional
considerations apply:
As the connection of these modules in parallel can result in high currents and stored energy,
the design of such a system should be made by a suitably qualified engineer.
All battery modules should be charged prior to installation as the modules may have
different states/levels of charge. Refer to the “Operation” section of this manual for
charging guidelines.
Do NOT install a fully discharged battery module into a fully charged bank of batteries.
Do NOT install a fully charged battery module into a fully discharged bank of batteries.
Do NOT mix these battery modules with other battery chemistry types without prior
engineered testing.
Do NOT mix these battery modules with LFP batteries from other manufacturers.
6.7
Series Connection
These battery modules are NOT designed for connecting in series. Connecting in series will void
your warranty as well as potentially creating a hazardous situation.