When valve clearance is correct, hold the pivot ball stud in place
with the allen wrench and tighten the rocker arm jam nut. Tighten
the jam nut to 174 in/lbs. torque. After tightening the jam nut,
recheck valve clearance to make sure it did not change.
Install new valve cover gasket.
•
Re-attach the valve cover.
•
NOTE:
Start all four screws before tightening or it will not be possible
to get all the screws in place. Make sure the valve cover gasket
is in place.
Install spark plugs.
•
Re-attach the spark plug wire to the spark plug.
•
On the GT-530 and GT-990, repeat the process for the other
•
cylinder.
3.10 MAJOR SERVICE MANUAL
To obtain a service manual for the generator, contact the near-
est Authorized Service Dealer. Make sure to identify the MODEL
NUMBER and SERIES. Manuals can be obtained from the internet
website or a service dealer.
3.11 DRIVE BELT
The engine drives the generator rotor by means of a pulley and
drive belt arrangement. Drive belt tension was properly adjusted
before the unit was shipped from the factory. If suspect that drive
belt tension is incorrect, contact an Authorized Service Dealer.
3.12 EXERCISING THE GENERATOR
The manufacturer recommends starting and operating the genera-
tor at least once every seven days. Let the unit run for at least 30
minutes to “exercise” the engine.
3.13 OUT OF SERVICE PROCEDURE
3.13.1 REMOVAL FROM SERVICE
If the generator cannot be exercised every seven days, and it is to
be out of service longer than 30 days, prepare the generator for
storage as follows:
1. Start the engine and let it warm up.
2. Close the fuel shutoff valve in the fuel supply line and allow
the unit to shut down.
3. While the engine is still warm from running, drain the oil
completely. Refill the crankcase with SAE 5W-30 oil having
API classification “For Service SF.”
4. Attach a tag to the engine indicating the viscosity and clas-
sification of the oil in the crankcase.
5. Remove the spark plug and pour two or three tablespoons of
clean, fresh engine oil into the spark plug threaded openings.
Reinstall and tighten the spark plug.
6. Remove the battery and store it in a cool, dry room on a
wooden board. Never store the battery on any concrete or
earthen floor.
7. Clean and wipe the entire generator.
3.13.2 RETURN TO SERVICE
To return the unit to service after storage, proceed as follows:
1. Check the tag on the engine for oil viscosity and classification.
Verify that the correct recommended oil is used in the engine
(see "Engine Oil Requirements"). If necessary, drain and refill
with the proper oil.
2. Check the state of the battery. Fill all cells of unsealed batter-
ies to the proper level with distilled water. DO NOT USE TAP
WATER IN THE BATTERY. Recharge the battery to 100 percent
state of charge, or, if defective, replace the battery.
3. Clean and wipe the entire generator.
4. Reconnect the battery. Observe battery polarity. Damage may
occur if the battery is connected incorrectly.
5. Turn OFF all electrical loads. Add fuel if necessary and then
start the engine.
6. Allow the unit to warm up thoroughly.
7. Apply electrical loads to at least 50 percent of the unit’s rated
wattage capacity.
8. When the engine is thoroughly warmed up, shut it down.
9. The generator is now ready for service.
3.14
RV GENERATOR SERVICE
INTERVAL
50 Hours ....................................................Clean Spark Arrestor
1st 50 Hours, then every 500 Hours ............... Adjust Valve Lash
100 Hours ............................................. Change Engine Oil/Filter
100 Hours ......................................................Clean Air Pre-filter
100 Hours ...................................................Inspect Spark Plugs
250 Hours .................................Replace Paper Air Filter Element
400 Hours ......................................................Replace Fuel Filter
500 Hours ..................................................Replace Spark Plugs
Maintenance
Содержание 004703-1
Страница 19: ...17 Notes...
Страница 20: ...18 Notes...
Страница 21: ...PART II INSTALLATION INSTRUCTIONS ONLY QUALIFIED ELECTRICIANS OR CONTRACTORS SHOULD ATTEMPT INSTALLATION...
Страница 25: ...23 Figure 1 2 Major Features and Dimensions Drawing No 0E1058 H General Information...
Страница 30: ...28 Figure 2 8 Compartment Floor Cutout Drawing 0G3529 A Installation...
Страница 42: ...40 Electrical Data Electrical Schematic V twin Drawing No 0E1057 F...
Страница 43: ...41 Electrical Schematic V twin Drawing No 0E1057 F Electrical Data...
Страница 44: ...42 Exploded Views Parts Lists Base Pulley Drawing No 0E1323 H...
Страница 46: ...44 Exploded Views Parts Lists Enclosure Drawing No 0G7865 C...
Страница 48: ...46 Exploded Views Parts Lists Engine Accessories Drawing No 0G7866 E...
Страница 50: ...48 Exploded Views Parts Lists Control Panel Drawing No 0E1013 B...
Страница 52: ...50 Exploded Views Parts Lists 760 V twin Engine Drawing No 0F1997 C...