OEC 9800 Installation Procedure
31
6.
Verify tracking by performing the following.
A. Place the tip of the Probe in the dimple located on the Transmitter.
B. Select the VERIFY button on the Visualization menu.
Note
:
The screen changes to the Visualization Option menu.
C. Select the SET VERIFICATION REFERENCE POINT button and verify that the button turns green.
D. Select the RETURN TO VISUALIZATION button.
7. Position the Transmitter approximately 4-inches from the top of the II.
Note
:
Use a book or some other object to position the Transmitter 4-inches above the II.
8.
Press an X-ray switch and verify an image is displayed on the left Workstation monitor.
9.
Select the CAPTURE IMAGE button on the FPD’s touch screen.
10. Verify that the image displayed on the Workstation’s left monitor is also displayed on the FPD.
11. Touch the Probe to the dimple on the Transmitter and verify that you can see the Probe’s icon (green line with red dot) in the
image on the FPD.