GEH-1791
ACCEPTANCE TESTS
Immediately upon receipt of the relay, an inspection and acceptance test should be
made to make sure that no damage has been sustained in shipment and that the relay
calibrations have not been disturbed.
If the ex ami nation or tests indicate that
readjustment is necessary, refer to the section on
SERVICING.
VISUAL INSPECTION
Check the nameplate stamping to make sure that the Model Number and rating of the
relay agree with the requisition.
Remove the relay from its case and check that there are no broken or cracked molded
parts, or other signs of physical damage, and that all screws are tight.
Check that the short fingers are in the correct location, as indicated in Figure 9
and Figure 10, and that the auxiliary brushes are properly adjusted (see Figure 13).
MECHANICAL INSPECTION
1.
Check that the rotating element moves without noticeable friction.
2.
Remove the time-dial locking screws and check that the moving contact just
touches the stationary contact when the time dial is set at 0.
The contact
wipe should be approximately 1/3211•
3.
Check that the control spring is not deformed, and that the spring convolutions
at No. 5 time-dial setting are reasonably concentric.
ELECTRICAL TESTS
Connect the relay as shown in Figure 11 and check the following:
1.
Check that with at least 115 volts, 60 cycle single-phase source connected to
both operating coils the relay picks up with approximately the time delay shown
in Figure 8.
2.
Check that the relay picks up at a
200
closing angle (or other closing angle
that is used) within � 30 when connected to a 115 volt, 60 cycle source with
rated voltage in both coils.
Check 0 displacement pickup, which should agree
with the value in Figure 1 within ! 10 %.
3.
With both coils connected to a 115 volt source with 0 displacement, check that
pickup time agrees with values given in Figures 5 or 6 ! 10%.
INSTALLATION PROCEDURE
If after acceptance tests the relay is held in storage before shipment to the job
site, it is recommended that the visual and mechanical inspection described under
the section on
ACCEPTANCE TESTS
be repeated before installation.