EntelliGuard R Circuit Breaker Retrofill AKD-10 Installation Manual DEH41550 R06
Install AKD-10 & substructure type 3200, 4000 & 5000A Retrofill Breaker
.
To remove the exiting breaker follow instructions provide with the legacy breaker and or switchgear/
switchboard. Note that one must remove the two ½-13 bolts holding the breaker down on the drawout tray
assembly found at the front of the tray. Notice how the breaker is located at the rear by two pins passing
thru the old breaker frame. Notice how the rejection plates underneath the legacy breaker align with
rejection pins on the drawout tray assembly. Verify the correct breaker is being used. Compare the rejection
plate arrangement on the new breaker to those on the old breaker
After the existing breaker is removed and the compartment updated with any added features, the pre-wired
breaker can be installed in the GE AKD-10 Switchgear, GE Switchboard or OEM Equipment.
1.
Verify that the new breaker is in the disconnected and OPEN position.
2.
For WPS-32/WPH-32/WPX-32/WPS-40/WPX-40/WPS-50/WPX-50 Retrofill Breaker.
A.
It is best to use Lifting Bar GE Part number
0247B8961G001
for 3200-4000A and
0247B8961G003
for 5000A and a suitable hoist to lift from above as shown in Figure 12A. (These
lifting bars have been tested to 200% of their 700 lb ratings.)
B.
Alternate method, use a lifting chain and hooks rated at least 1400 lbs to lift the breaker from
above as shown in Figure 12B. (chains must not be at an angle less than 45 degrees from the
horizontal plane.) Installation in upper compartments may not be possible with limited overhead
space or the GE switchgear hoist.
Figure 12. AKD-10—Location of Hooks
Figure 12A. AKD-10—Using GE Lifting bar
and hoist
Figure 12B. AKD-10—Using Chain And
Hook
3.
Make sure that the lifting bar or generic chain-hooks are secured and locked in place.
Dropping a
breaker can result in injury or death.
4.
Line up the breaker in front of the compartment where it will be installed; then raise it slightly above
the height of the drawout Rail assembly.
5.
Pull out the Rail assembly beneath the breaker.
6.
Lower the breaker down on the Rails. .
7.
Remove the lifting bar and or chains.
8.
Push the breaker into the compartment slowly while observing the alignment of the secondary
disconnects and opening of the optional shutter. A compartment interlock rod in the right front will
ride over a cam and drop into position in the DISCONNECT position
.