7.   Initialize the sensitivity adjustment:

Turn the sensitivity adjustment drum to the left (increasing 
numbers on the scale) as far as it will turn. Then turn it one 
(1) complete rotation to the right (decreasing numbers on the 
scale).

8.   Apply a “False Signal” to the sensing port of the VRP-B-CH:

The “False Signal” pressure should be equivalent to the 
desired setpoint pressure. Refer to the original invoice 
paperwork supplied with the product for the appropriate 
setpoint pressure setting. If the adequate gas pressure is not 
available from the pipeline, a nitrogen bottle with regulator 
may be utilized to introduce the proper “False Signal” pressure. 
Additionally, an SP series setpoint adjustment pump may be 
used to provide a false signal pressure above the available 
pipeline gas pressure.

Note: It is recommended that a calibrated pressure gauge be 
used to ensure accuracy of the “False Signal” pressure.

9.   Adjust the setpoint adjustment screw:

Turn the setpoint adjustment screw on top of the VRP-B-CH 
unit until cylinder top and cylinder bottom pressure gauges 
show equal pressure. Clockwise rotation decreases cylinder 
bottom pressure. Turn setpoint adjustment only when 
pressures are not equal.

Note: For pilots venting to atmosphere in control, continue, 

otherwise, skip forward to the adjustment section for pilots 

bleeding to a pressure system.

10.  Final sensitivity drum adjustment

Turn the sensitivity adjustment to set the cylinder top and 
cylinder bottom equal to power gas pressure. When equal, 
the exhaust port should stop bleeding gas. If not, turn the 
sensitivity adjustment drum to the left (increasing numbers) 
until the exhaust port just stops bleeding.

11.  To check the deadband, Turn the setpoint adjustment screw 

clockwise until the cylinder bottom pressure just drops off. 
Then turn the setpoint adjustment screw counterclockwise 
until the cylinder top pressure just drops off. Keep track of the 
total rotation of the screw. Now place the setpoint adjustment 
screw in the middle of this rotation.
Turn the sensitivity adjustment drum to the right (decreasing 
numbers) until the exhaust port just starts bleeding gas. 
Check the total deadband again and repeat this process until 
the deadband is eliminated and the following criteria is met:
With a 3/4 percent change in the sensing pressure (above  
and below setpoint), the cylinder top and cylinder bottom 
pressure should develop a pressure differential equivalent  
to 20 percent of power gas.

Example: 
Power gas = 100 psig
Orifice #3 top, #3 bottom
Setpoint = 400 psig
With a change of the sensing pressure to 403 psig, the cylinder 
top pressure should drop at least 20 psig.
With a change of the sensing pressure to 397 psig, the cylinder 
bottom pressure should drop at least 20 psig.

If the Pilot sensitivity is greater than this, bleed gas may further be 
reduced by turning the sensitivity again to insure the pilot meets 
the minimum criteria.
For VRP-B-CH pilots bleeding to a pressure system
10.  Leave the pilot vent port attached to the system it normally 

discharges to and insure this discharge line is open. The pilot 
is properly adjusted when both gauges are equal at the pilots 
desired setpoint, the cylinder pressure are set at 90 percent 
of the power gas, and any movement to the adjustment drum 
causes an immediate response from the pilot output gauges. 

11.  Verify “False Signal”:

Upon achieving setpoint, inspect the gauge which measures 
the “False Signal.” If the “False Signal” has deviated, readjust 
it to attain proper pressure. Remember that the “False Signal” 
applied to the VRP-B-CH sensing port should be equivalent to 
the desired pressure setpoint of the pilot. Upon readjustment 
of the “False Signal” repeat steps 10 & 11 until setpoint  
is achieved.

12.  Remove “False Signal” pressure from sensing port of 

VRP-B-CH.

13.  Open valve on sensing line.

14.  Open cylinder block valves:

Opening the cylinder block valves will reestablish 
communication between the VRP-B-CH and the control 
valve actuator and put the system back into service. Exercise 
caution when putting the VRP-B-CH into service to prevent 
unintended closure/opening of the valve.

Regulator is now ready for service.

The initial adjustments are utilized to set the VRP-B-CH at a point 
approximating the desired setpoint. In order to achieve optimum 
accuracy of setpoint and sensitivity, the fine tuning procedures 
need to be completed.

Fine Tuning Procedures

To change the VRP-B-CH setpoint only:
In the case where the VRP-B-CH only requires a change in  
setpoint only, the setpoint adjustment may be rotated to  
achieve a new setpoint while the VRP-B-CH is in service.  
No other adjustments need to be made. GE recommends  
noting the setpoint change per revolution of the control spring 
installed in the pilot. Setpoint change per revolution of the  
control spring can be found in the table entitled VRP-B-CH  
Pilot Selection Chart on page 6 of this manual.

To change the VRP-B-CH sensitivity:
In the event that the VRP-B-CH requires a change in to the 
sensitivity adjustment, the setpoint adjustment will also require 
adjustment. Any changes in the sensitivity adjustment affect  
the setpoint adjustment. A decrease (higher numbers) in the 
sensitivity of the pilot, will require the setpoint adjustment to be 
decreased. An increase (lower numbers) in the sensitivity of the 
pilot, will require the setpoint adjustment to be increased.

Once adjusted, the Becker VRP-B-CH pilot typically requires  
very little or no readjustment.

Troubleshooting

Control problems generally fall into one of the following  

Содержание Becker VRP-B-CH Series

Страница 1: ...GE Oil Gas Becker VRP B CH Series Valve Regulator Pilots Instruction Manual GE Data Classification Public...

Страница 2: ...b GE Oil Gas 2016 General Electric Company All rights reserved...

Страница 3: ...GULATIONS APPLICABLE AT THE SITE AND THE PARTICULAR REQUIREMENTS FOR OPERATION OF OTHER EQUIPMENT AT THE SITE THESE INSTRUCTIONS DO NOT PURPORT TO COVER ALL DETAILS OR VARIATIONS IN EQUIPMENT NOR TO P...

Страница 4: ...to increase their performance while retaining simple operation and low maintenance Technical Assistance Should you have any questions please contact your local GE sales representative or technical as...

Страница 5: ...percent Applications Primary pressure control Overpressure protection monitor Underpressure protection standby Relief valve Backpressure control Unique Bleed to Pressure System BPS when feature can b...

Страница 6: ...arts AL 2024 Anodized Aluminium 316 Stainless Steel Internal Parts 316 Stainless Steel 2024 Anodized Aluminum Springs Plated steel Diaphragms Buna N with nylon reinforcement Seats and O Rings Buna N T...

Страница 7: ...8239 3 0 psig 21 kPa 16 5 psig 114 kPa 35 psig 241 kPa 20 85 psig 138 596 kPa Pink 25 8240 6 4 psig 44 kPa 35 2 psig 243 kPa 65 psig 448 kPa 50 175 psig 345 1207 kPa Yellow 25 1306 23 psig 157 kPa 125...

Страница 8: ...e the bottom piston moves away from the balance valve plunger and maintains pressure on the bottom of the actuator cylinder This causes an increase in cylinder bottom pressure and a decrease in cylind...

Страница 9: ...series non bleed sensor if equipped The DPS 2 non bleed sensor should be disabled prior to commencing initial adjustment procedures Failure to disable the DPS non bleed sensor may prevent initial adj...

Страница 10: ...psig With a change of the sensing pressure to 397 psig the cylinder bottom pressure should drop at least 20 psig If the Pilot sensitivity is greater than this bleed gas may further be reduced by turni...

Страница 11: ...the direction of speed adjustment is correct the closing speed should be smaller than the opening speed In order to find the optimum setting try several combinations of adjustable orifice settings 2...

Страница 12: ...ruction Note It is not necessary to replace any rubber goods in GE s Becker instrumentation or instrumentation accessories on a regular basis However common practice suggests that replacement of rubbe...

Страница 13: ...ies Valve Regulator Pilot Instruction Manual 10 2016 General Electric Company All rights reserved Notes 1 Item no 1 Is torqued to 140 160 in lb 2 Items no 21 and 28 are torqued to 95 100 in lb VRP B C...

Страница 14: ...95 2670 O Ring 115 8 30 7008 Cartridge Cap for 175 600 CH 9 98 3137 1 4 20 in x 3 4 in HHCS SS 10 2 98 3269 8 32 x 1 2 in SHCS Alloy FEP only 11 95 2671 O Ring 141 12 30 7007 Standard Tube Cap 13 25 1...

Страница 15: ...0 CH 14 25 1306 Yellow Spring 15 25 1562 Grey Spring for 1500 CH 800 1300 psig 16 25 8073 Violet Spring for 1500 CH 1000 1500 psig 17 30 7023 Spring Cart for 1000 1500 CH 18 30 7006 Standard Bearing C...

Страница 16: ...Bottom Spacer 4 95 2615 O rIng 012 5 25 1177 Bottom Piston Key Part Number Description 1 30 7016 Adapter Block 2 95 2665 O ring 145 3 98 3056 1 2 20 Jam Nut 316 4 30 7015 Thread Extension 5 30 7010 Sm...

Страница 17: ...e Minimum travel time the time the valve takes to move from one extreme position to another is achieved when the signal deviates 5 or operation The monitor or standby regulator pilot travel time is go...

Страница 18: ...stment information NBV Series No Bleed Valve Achieves non bleeding conditions at both full open and full closed positions without any adjustment Selection based upon power gas pressure and discharge g...

Страница 19: ...bottom seat E 1b Insert the balanced valve assembly C with the stem facing downward 1c Insert the second balanced valve assembly C with the stem facing upward 1d Insert the second strainer D1 and the...

Страница 20: ...nd secure the adjusting orifice K1 with nuts M1 in the orifice manifold K as shown 3 Seat the four 012 O rings L into the inlet and exhaust port recesses on the pilot body block F Note the orientation...

Страница 21: ...source to the orifice block K as shown Use approximately 100 psig for testing 4b With the pressure source activated soap test around the balanced valve assembly C on both the bottom and the top of th...

Страница 22: ...he outside piston U and into the groove near its base 6a Install one washer Z onto the shaft of the outside piston with the grooves facing upward 6b Install the convoluted diaphragm AA onto the shaft...

Страница 23: ...arking the diaphragm and the pilot body block F with a single line 8c Rotating the diaphragm assembly clockwise until it stops III 8d Marking the pilot body block F with a line extending from the exis...

Страница 24: ...que to 100 110 in lbs Figure 1 Assembling the diaphragm 175 CH Cartridge Assembly Insert 145 O ring F into the cartridge spacer G Place the cartridge spacer G between the diaphragm assembly and spring...

Страница 25: ...ring 046 K1 in the O ring groove in the bottom flange K as shown Place the spacer N inside the bottom flange K 175 CH Piston Assembly Place Diaphragm Assembly onto Spacer N Making sure not to twist Di...

Страница 26: ...ved 175 CH Spring Chamber Assembly Bolt Spring Chamber H onto Cartridge Spacer G using six 6 Fiberglass Washers P and six 6 1 4 20 x 7 8 SHCS Q Bolt Bottom Flange K into Cartridge Spacer G using eight...

Страница 27: ...Figure 7 Connecting the pistons 600 CH Spring Chamber Assembly Bolt the spring chamber D to the top body assembly H using six 6 fiberglass washers J and six 6 1 4 20 x 2 inch SHCS K Figure 8 Bolting t...

Страница 28: ...ly L Place the adapter block assembly onto the bottom spacer K Making sure not to twist the diaphragm C thread the small piston B into the outside piston M by holding the spring chamber H and rotating...

Страница 29: ...Assembly For 1500 CH Press fit the thrust bearing A into the bearing case B For all other CH models press fit the thrust bearing A into the bearing case C Figure 13 Thrust bearing assembly Bearing Nu...

Страница 30: ...bly Make sure that the spring J touches no part of the screw E when spinning If the spring J does touch any part of the screw E then replace the spring J and repeat the test If the spring J is satisfa...

Страница 31: ...ile pushing the cap B down When firm engagement of the cap B is felt orient the cap B so that the mounting holes are in line with the top body assembly F pressure ports Bolt the cap B to the spring ch...

Страница 32: ...chamber G using twelve 12 1 4 20 x 3 4 inch HHCS H Figure 22 Bolting the cap to the spring chamber 1000 1500 CH Thread Seal Assembly Place 7 16 inch SS thread seal I and 7 16 inch SS flat washer J on...

Страница 33: ...Becker VRP B CH Series Valve Regulator Pilot Instruction Manual 30 2016 General Electric Company All rights reserved Parts Silhouettes...

Страница 34: ...31 GE Oil Gas 2016 General Electric Company All rights reserved Parts Silhouettes...

Страница 35: ...Becker VRP B CH Series Valve Regulator Pilot Instruction Manual 32 2016 General Electric Company All rights reserved 30 7011 SMALL DIAPHRAGM FOR 1000 1300 CH SENSING ASSEMBLY Parts Silhouettes...

Страница 36: ...ax 81 03 6890 4620 KOREA Phone 82 2 2274 0748 Fax 82 2 2274 0794 MALAYSIA Phone 60 3 2161 0322 Fax 60 3 2163 6312 MEXICO Phone 52 55 3640 5060 THE NETHERLANDS Phone 31 15 3808666 Fax 31 18 1641438 RUS...

Отзывы: