Abbreviated Installation Instructions
(For those who don't have time!)
GDS 240PP operator
Place the operator in correct position. Pinion wheel to be
parallel to the gate, and stepped out to allow for width of
rack once it is mounted onto the gate frame. Mark out
fixings and fix operator to the concrete pad.
Fix rack to the gate frame keeping 1mm-2mm clearance between
the rack teeth and Pinion wheel
Once the rack is fixed move the gate and sight the rack
moving over the pinion wheel, check that most of the pinion
wheel meshes with the rack. Make sure rack runs freely over
the pinion wheel, any tights spots should be corrected by
adjusting the rack height. Check the operator is firmly bolted
down to the concrete pad.
Ensure stops are installed on the gate for the fully closed and fully
open positions.
Connect required P.E Beams. Fit limit brackets to actuate at
gate end positions. Connect Power supply. Turn on Power.