MECHANICAL INSTALLATION
The installation of the double-glass bifacial module shall match the photovoltaic support
design and the customized accessories, and comply with the system design requirements.
It is necessary to use the specified clamp for the module installation, and the torque force
shall meet the requirements.
Horizontal installation: the first module and the last module of every row shall be fixed
with the side-clamp, and the Modules in the middle should be fixed by middle-clamp.
Vertical installation: the first module and the last module of every line shall be fixed with
the side-clamp, and the Modules in the middle should be fixed by middle-clamp.
To avoid the clamp producing the shade on the front or back of the module.
side-clamp
middle-clamp
Figure 3 Structural breakdown schematics of
side-clamp
Figure 4 Structural breakdown schematics
of middle-clamp
Installation tool: 13mm socket wrenches (electric wrenches optional), torque wrenches
10-100 N.M; Tightening torque of the clamp: 16 N.M
~
20N.M.
Side clamp, middle clamp: including lower and upper EPDM blocks, fastener
combination (M8 bolt, washer, spring washer, nut).