1) Remove 8 screws and seperate the
gas valve from the flange.
2) Place the nozzle between the gas valve
and the flange (with the O-ring)
according to the boiler model.
3) Replace the disassembled companents
after the nozzles installed with the
care of tightness. Use the flue gas
analyzer to provide the values which
are given in the table of values for LPG.
43
Before the commissioning of the boiler,
all parameters must be regenerated
according to the LPG. This process must
be
made
by
authorized
Gassero
services.