Installation, Operation and Maintenance Manual
Pressure Regulating Valve – Model Ares N
MI–42
Prepared by
Verified by/ Approved by
CSQ
Date
Revision
Page
José Junior
Vanízio Lizo
Jamerson
24/03/17
02
10 of 21
5) All necessary pressure-sensing pick-ups, downstream of the equipment pipeline, were provided respecting the
dimensions recommended by the manufacturer.
6) A pressure gauge, or any other pressure-measuring device, was foreseen for the upstream and downstream of the
equipment to allow for the correct setting up at the operation start-up.
7) A vent line was planned between the regulator and the first outlet shut-off valve to assist the operator during start-up.
8) Check the flow direction marked on the body of the pressure-regulating valve and pay attention at the time of its
installation so that it is properly positioned.