Page 16
4990497003 Date: 11/2016
TR20 Installation, Operating & Maintenance Manual
4
Commissioning
4.1
Pre-commissioning check list.
Figure 11. Commissioning Tappings
4.2
Inlet commissioning filter.
The inlet commissioning filter should have been in place throughout the installation
of the TR20 and its pipework.
The filter should be removed during commissioning after 15 minutes operation at
900 rpm.
4.3
Monitoring probes.
Two 1/4” BSP blanking plugs are fitted in each of the inlet port flange and
unused outlet port blanking flange.
These should be removed and replaced with a temperature probe and a
pressure probe for commissioning only. (see Fig. 11)
If Gardner Denver supplied flanges are not used, the installer must provide 2 x 1/4”
BSP tappings adjacent to the inlet and outlet ports for the commissioning test
probes.
Failure to remove the
comissioning filter during
commissioning may lead to
failure of the compressor.
CAUTION
Lubrication plugs fitted.
Gearbox filled with oil.
Pipe bores etc cleaned after fabrication.
Commissioning filter in position.
All flanges, fasteners and mountings secure.
Vehicle PTO disengaged.
Engine management system set-up correctly for the application.
Commissioning temperature and pressure probes fitted (see fig. 12)
Blow (ball) valve open (if starting against a tank pressure).
Commissioning 2.5”-3” gate valve and silencer fitted.
Ancillaries correctly fitted and sequenced.
Tick when completed