background image

Page 14

4990497003   Date: 11/2016

TR20 Installation, Operating & Maintenance Manual

Figure 10a Absorptive, separate ancillaries.

OPTION B

OPTION A

Installation

3.9 

 

Package 1 -  Separate ancillaries with    

 

 

 

 

absorptive discharge silencer

Compressors should never 

be started against pressurised 

discharge lines or tanks.

CAUTION

** 

- Indicates optional item.

*

 - Indicates customer supplied pipework.

Ref. No. 

Description

TR20 Basic M/C

Inlet Filter

3.75” Hose Clip

Hose Adaptor (Cuff)- Nitrile

Ducting -2m x 89mm Bore

Inlet manifold - TR20

Inlet gasket

Commissioning Filter

9             Gasket - Outlet Port

10 

Outlet Blanking Flange                                     

Ref. No. 

Description

 11 

Outlet Flange (S0W) - 77mm Bore

 12 

Relief valve - 1.25”, 2.5barg

 13 

Flange TW1 (S0W) - 80mm Bore

 14 

Gasket, 90mm NB, TWI

 15 

2.5” Absorptive Discharge Silencer

 16 

Check Valve Kit (3” BSP Outlet)

 17 

Shear Coupling (K1310/DIN100)

 18 

Friction Coupling (K1310/DIN100)

 19 

Storz Coupling - 3” BSP                               

 20          Inlet Blanking Flange

 21          Secondary Outlet Gasket

 22          Secondary Outlet Flange

2

9

12

11

14

15

16

13

13

4

3

5

4

3

6

7

8

18

7

20

10

9

21

22

1

13

*

*

*

*

19

17

**

14

**

**

Содержание TR20 Rear ACW

Страница 1: ...TR20 SCREW COMPRESSOR Models TR20 Rear ACW TR20 Rear CW Installation Operating Maintenance Manual Original Instructions November 2016 4990497003...

Страница 2: ...lignment 10 3 6 Pipe work 12 3 7 Commissioning filter 12 3 8 Ancillaries 13 3 9 Package 1 layout parts 14 3 10 Package 2 layout parts 15 4 Operating and Commissioning 4 1 Pre commissioning check list...

Страница 3: ...on A relief valve must be fitted in the outlet pipe work as close to the compressor as possible The valve must be positioned so as not to vent air onto any personnel since the air discharged will be h...

Страница 4: ...es synchronised screw rotors combined main body step up gearcase assembly and inlet bearing carrier The compact shape and size of the compressor make it ideal for mounting inside the chassis on most v...

Страница 5: ...lied as separate items including the absorptive type discharge silencer and inlet filter kit Package 2 Loose ancillaries with reactive discharge silencer Standard ancillaries supplied as separate item...

Страница 6: ...foreseen operating environment is as follows Ambient temperature range 40 to 50 C Resistant to tropical rain in operation and transit salt and sun Humidity level Up to 100 RH condensing Vibration leve...

Страница 7: ...ng valves must be positioned so that hot air cannot vent onto the operator or the compressor Silencers should be fitted as close as possible to the discharge port For the recommended layout of the mac...

Страница 8: ...ies are shown below Installation Figure 4 Mounting Drive options An incorrect drive rotation will damage the compressor CAUTION Outlet Inlet The basic TR20 compressor should be installed mounted using...

Страница 9: ...plug holes approximately 2 5 litres total if necessary Key 1 Magnetic drain plug and washer 2 Fill plug and washer Figure5 MountingDetails separateancillarypackages Alternative mounting channels maybe...

Страница 10: ...ne shaft and drive coupling should be clean and damage free to help ensure the flange fits correctly Both tapers should be smeared with a light oil to aid future separation The companion flange should...

Страница 11: ...Adaptor SAE 3 1 Washer 4 1 Key Parallel Rectangular Round End 10 x 8 x 50 Long 5 1 Socket Head Cap Screw M12 x 40 Long Figure 8 Drive Alignment The compressor should be mounted so that the prop shaft...

Страница 12: ...ld be followed to prevent damage to the machine and contamination of the discharged product All inlet pipework must be stainless steel or thick wall aluminium to help prevent corroded particles enteri...

Страница 13: ...or connecting pipework to the silencer should be incorporated where this could occur Check non return valve This is to prevent a back flow of air and product often encountered when stopping compresso...

Страница 14: ...ter 3 3 75 Hose Clip 4 Hose Adaptor Cuff Nitrile 5 Ducting 2m x 89mm Bore 6 Inlet manifold TR20 7 Inlet gasket 8 Commissioning Filter 9 Gasket Outlet Port 10 Outlet Blanking Flange Ref No Description...

Страница 15: ...t manifold TR20 7 Inlet gasket 8 Commissioning Filter 9 Gasket Outlet Port 10 Outlet Blanking Flange Ref No Description 11 Outlet Flange S0W 77mm Bore 12 Relief valve 1 25 2 5barg 13 Flange TW1 S0W 80...

Страница 16: ...probe for commissioning only see Fig 11 If Gardner Denver supplied flanges are not used the installer must provide 2 x 1 4 BSP tappings adjacent to the inlet and outlet ports for the commissioning tes...

Страница 17: ...5 minutes depress the clutch and disengage the PTO 5 Check the oil fill level and drain plugs for leaks and replace the commissioning filter with the inlet gasket supplied being careful to remove any...

Страница 18: ...Manual Commissioning Figure 12 Commissioning Tests No Description 1 Pressure Manometer 2 Temperature Gauge 3 Pressure Tapping Inlet depression 4 Temperature Tapping Inlet 5 Commissioning Filter 6 Pres...

Страница 19: ...l Connet pressure lines Check inlet filter has no blockages Ensure tanker is not pressurised Ensure pressure lines are open If pressurised open ball valve on the tanker Starting the compressor Check t...

Страница 20: ...essor Return the engine speed to tick over Disengage the PTO Stop the engine 4 6 TR20 Driver training All drivers should be given training including Safety Instruct the driver regarding Rotating parts...

Страница 21: ...USTOMER VEHICLE REG VEHICLE MAKE VEHICLE MODEL PTO TYPE RATIO ENGINE SPEED COMMENTS TIME DURATION INPUT SPEED Rpm PRESSURE BAR g BARO m bar INLET DEPRESSION RELIEF VALVE LIFT RELIEF VALVE BYPASS RELIE...

Страница 22: ...ter element Check Relief Valve function setting and visually Maintenance 5 1 Schedule 5 5 2 Changing the gearcase oil see fig 6 1 Remove the magnetic drain plugs and sealing washers can also remove th...

Страница 23: ...operating at greater than 85 of its pressure setting Setting 85 2 bar g 1 7 bar g 2 2 bar g 1 87 bar g Operation Function Test 1 Rotate the lifting screw ACW until a clear audible air discharge is pro...

Страница 24: ...ng If this indicator shows red when the compressor is operating then the filter must be cleaned or replaced as follows To clean the casing it may be necessary to unbolt the filter casing from the vehi...

Страница 25: ...TR20 Compressor Serial Number MONTH 1 2 3 4 5 6 7 8 9 10 11 12 Oil Level Relief valve Air Filter Security MONTH 1 2 3 4 5 6 7 8 9 10 11 12 Oil Level Relief valve Air Filter Security MONTH 1 2 3 4 5 6...

Страница 26: ...Ind Australia Pty Ltd 30 Bearing Road Seven Hills New South Wales 2147 Australia Phone 61 2 96207000 Fax 61 2 96207955 email hermant malik gardnerdenver com France Gardner Denver France SA Division C...