Installation:
Stage 1
Page 5 of 22 // email [email protected] tel: +44 (0) 1438 833577 fax: +44 (0) 1438 833565
SPS 800 / 1200 - Sliding Panel System Plasma Ad-
Before You Begin 1
Preliminary Checks
The enclosure to house the mechanism
should be completely finished prior to
installing the mechanism. It is important
to check various dimensions against
the Technical sheet for this mechanism
prior to starting the installation. This will
highlight any errors which may make
installation impossible.
It is well worth setting up the mecha-
nism out of the cabinet to familiarise
yourself with the general operation.
Set up as shown. The drive unit shafts
engage with the couplers on the panel
mechanism. See detail A, right. The M5
x 35mm bolts connects them.
Plug the units together with the leads from the control box. The panel mechanism
connection can be found tucked in one end of one of the mechanisms. See sheet 3
for further details of the electrical connections. Plug the infrared receiver cable into
the 3.5mm Jack connector.
Plug into the mains and press 'OUT' on the remote control. The panel mechanism
should initially move back and then move off to the side. The plasma advance unit
should then move out. Pressing 'IN' on the control reverses the operation. 'STOP' is
the Stop.
Do not adjust any of the cams on the mechanism.
They are factory set to the correct positions. If you
think you need to make adjustments to the cam
please contact Future Automation first.
NOTE:
Panel Advance Shaft rotates 180 degrees
to create a forward-back motion of 40mm.
If out of sync by 180 degrees it may jam.
Panel
Moving
Shaft
Panel
Advance
Shaft
NOTE:
The mechanism is set up to move
about panel 30mm.