Installation
Mounting the subsystem in the rack
Ê
If required, you can mount one additional a cable clip for vertical cable
routing.
Ê
Place the cage nuts and/or the spring nuts in the groove of the support
uprights and/or of the support bracket at the marked attachment points.
Ê
If necessary, adjust the position of the nuts in the groove until they lock into
the correct position.
Ê
Follow the installation instructions for cage and spring nuts in your rack
manual.
Ê
Secure the two carrier rails left and right on the support uprights and/or on
the support bracket in the rack using the Allen key No. 5. Please note that
the guide nubs of the rails next to the spring nuts must fit into the holes in the
support uprights and/or in the support bracket.
Ê
Slide the subsystem unit into the rack and fasten it to the rack using the four
knurled screws.
To remove the subsystem, follow the same procedure in reverse order.
3.3.1
Routing cables
The articulated cable guide for routing the cables is located on the inside of the
DataCenter rack (on the right, if you are looking at the back of the rack). Please
refer to the chapter “Cable Management” in the manual for the DataCenter rack
for information on how to route the cables.
In other rack versions, the cables are routed using the cable channels on the
support uprights.