4.3.7 Closing the wall penetration
❒ Pack the space in the wall penetration with a non-flammable insulating material
➥ The partition must be insulated to conform with ÖNORM B 3836 or DIN
4102-11!
❒ Close the wall penetration on the store side and the boiler room side with a non-
flammable covering
NOTICE
Do not connect the transfer channel to the brickwork (with concrete), as this will
transfer sound through all the brickwork.
4.4 Connecting the system
4.4.1 Electrical connection
DANGER
When working on electrical components:
Risk of electrocution!
When work is carried out on electrical components:
❒ Only have work carried out by a qualified electrician
❒ Observe the applicable standards and regulations
➥ Work must not be carried out on electrical components by unauthorised
persons
❒ Lay cables of components to control cabinet
➥ Lay the cables so that nobody will trip over them!
➥ Do not lay the cable over or around sharp edges!
❒ Wire the connections according to the wiring diagram
4.4.2 Connecting the sprinkler system
Connection should only be carried out by authorised technicians.
When connecting the sprinkler system, please also note:
❒ Put a stopcock and bolted joint in front of the thermal discharge safety device
➥ Important for easy dismantling in the event of maintenance work!
Assembly
4
Assembling the torsion arm agitator
Installation Instructions TGR 110/150/200 | M1390116_en