❒ Secure the cyclone container to the rotary valve unit
➥ Note the cut-out for the drive ratio (A) of the rotary valves!
❒ Remove the cover from the control cabinet
❒ Undo the four screws on the control cabinet holder
❒ Hang the control cabinet on the screw heads and tighten the screws
❒ Wrap thermal insulation around stoker duct as shown
❒ Remove the cover on the cable duct and lay the cables of the components via the
side panel to the control cabinet of the boiler
⇨ See "Connect the suction unit components" [page 40]
❒ Loosen both screws below the cable duct on the stoker
❒ Push temperature sensor under clamping plate and fix with screws
❒ Lay the cable for the temperature sensor cable via the cable duct to the boiler
controller
5
Assembly
Assembly work