MC13853 LNA Evaluation Board User’s Guide, Rev. 1.3
Freescale Semiconductor
3-1
Chapter 3
Basic Test Equipment Setup
3.1
Overview
To test and evaluate the performance of the MC13853 LNA on its EVB environment, a test plan and a test
equipment bench set-up in the lab is necessary. A basic test plan can be made by following the MC13853
data sheet and obtaining the same measured parameters. However, the results are dependent on the test
equipment configuration. In order to establish a basic test set-up, the details and equipment
interconnections are given in
All test equipment used must be calibrated with a valid calibration due date. Also, it is important to perform
an internal instrument calibration of the main items, such as the RF digital signal generator, the spectrum
analyzer and function generator. Since the RF power and its sensors require a separate calibration
procedure, it is very important that this is done before valid data is taken.
Once the test equipment is configured and connected, a bench calibration must be conducted at the
frequencies of interest in order to determine the offset values for the RF power meter and spectrum
analyzer.
The DC and control interconnecting cable harness is detailed in the
Appendix A, “DC and Control Wiring
”. This should be available before the test and evaluation of the MC13853.
There are three test equipment setups required to make all of the measurements. The following steps are
recommended:
1. From the list of test equipment given in
Section 3.2, “List of Test Equipment
,
assemble the line-up as given in
, and
2. Calibrate each individual instrument first following the manufacturer’s procedure.
3. Calibrate the RF power meter and its sensors at the desired band and frequencies.
4. Conduct a bench calibration at each required frequency. Record all results and enter these as offsets
into the RF power meter and spectrum analyzer.
5. Test the set-up without the evaluation board and verify that the bench calibration is correct by
setting the RF digital signal generator level to 0 dBm at the desired band and frequency.
6. If (5) fails, repeat steps (1) through (4) until measurements are correct.
7. If (5) passes, connect the MC13853 into the circuit.
Содержание MC13853 LNA
Страница 1: ...Document Number MC13853EVBUG Rev 1 3 10 2007 MC13853 LNA Evaluation Board User s Guide...
Страница 4: ...MC13853 LNA Evaluation Board User s Guide Rev 1 3 iv Freescale Semiconductor...
Страница 14: ...Initial Instructions MC13853 LNA Evaluation Board User s Guide Rev 1 3 1 8 Freescale Semiconductor...
Страница 20: ...Basic Test Equipment Setup MC13853 LNA Evaluation Board User s Guide Rev 1 3 3 4 Freescale Semiconductor...
Страница 22: ...DC and Control Wiring Harness MC13853 LNA Evaluation Board User s Guide Rev 1 3 A 2 Freescale Semiconductor...