31
PURE VIEW: Al
13
HOME GLASS BALUSTER INSTALLATION
Fig. 1
Fig. 2
Fig. 3
Fig. 4
OTP
and Proud Post: Max Post Spacing
• 8’
panel maximum post spacing is 93-7/8”.
• 6’
panel maximum post spacing is 69-7/8”.
Note: Do not exceed the maximum post spacing.
8’
Panel max post spacing 93-7/8”
6’
Panel max post spacing 69-7/8”
OTP
and Proud Post: Measuring The Panel Opening Length
• Measure the distance of the panel opening.
• Measure from the back wall of the bracket to the back wall of
the bracket on other post.
• Confirm that the measurements for the top brackets are the
same as the bottom brackets.
Measure the panel opening
Not here
Measure from
back of bracket
Check measurement with top
3/12
OTP
and Proud Post: Max Post Spacing
• 8’
panel maximum post spacing is 93-7/8”.
• 6’
panel maximum post spacing is 69-7/8”.
Note: Do not exceed the maximum post spacing.
8’
Panel max post spacing 93-7/8”
6’
Panel max post spacing 69-7/8”
OTP
and Proud Post: Measuring The Panel Opening Length
• Measure the distance of the panel opening.
• Measure from the back wall of the bracket to the back wall of
the bracket on other post.
• Confirm that the measurements for the top brackets are the
same as the bottom brackets.
Measure the panel opening
Not here
Measure from
back of bracket
Check measurement with top
3/12
45
o
Butt These
Two Faces
Bracket Has
To Be Set At
This Setting
Bottom of
Bracket
1. Install ATRs and Spacers opposite of the Angle Bracket first.
2. Measure from the inside of the post and add 2” [51mm] to
the over all length.
3. Install ATRs and Spacers on the Angle side measuring from
the end of the Bracket Cup adding 2-1/2” [63.5mm] to the
overall length.
4. Once both ATRs are installed center Angle Splice over Angle
Bracket.
5.
Secure Angle
Splice on ATRs with a Rubber Mallet.
Note:
• ATR should overhang Post 1” [25.5mm] in each side.
Step 2:
ATR Angle Splice (OTP)