At each re-calibration or repair following checks or actions have to be done: 
 

1.  All bottom parts of the cable glands are sealed to the housing with some gasket. You have to check 

the existence and the condition of these gaskets, the gaskets have to be replaced if required. 

2.  You have to check all bottom parts of the cable glands for a firm seat in the housing. 

(Recommendation: use a 12-point ring spanner with a cut-out and metric size 19 mm, if the cable are 
already installed). 

3.  All cable gland nuts must be tightened. A cable gland nut is tightened correctly if the cable gland 

constricts the cable jacket (not the shrink tube!) significantly! The cables must not run sloped in the 
cable glands. 

4.  Unused cable inlets must be closed by a blind plug. If a cable gland nut is correctly tightened the 

sealing part of the cable gland must constrict the blind plug significantly! 

5.  An eventually existing pressure compensating valve has to be removed. The corresponding hole 

must be closed by a blind plug and a gasket. 

6.  The earth screw must be electrically connected with protective earth (potential equalisation). 

For doing this only the upper nut should be loosened and tightened again. The lower nut (= counter 
nut) and the earth screw with washer must not be rotated or loosened – the gasket is bonded! 
If loosened by accident the earth screw must be re-inserted and locked with some Loctite. 

7.  Before you will close the junction box you must check the cover and the cover sealing for any dirt or 

damage. Replace the cover sealing if required, otherwise a proper sealing is not assured. 
Generally you have to use the red sealing made of silicone. You can improve the quality of this 
silicone sealing (it must be the red one!) by using a suitable grease (e.g. sanitary grease for fittings). 

8.  Before you close the cover again you have to place 2 new dry tablets within the junction box. 
9.  The cover screws always have to be tightened crosswise and equally unless the cover is attached to 

the junction box. 

10.  Generally the inside of the junction box must be totally dry before you can close the cover 

 

Junction Box Type KPF – Technical Manual, Rev. 1.11   July 2008

 

Page 7 of 8

Содержание KPF-4

Страница 1: ...Junction Box Type KPF 4 KPF 6 KPF 8 KPF 10 T TE EC CH HN NI IC CA AL L M MA AN NU UA AL L Flintec GmbH Bemannsbruch 9 74909 Meckesheim GERMANY www flintec com...

Страница 2: ...the use of any options or any consumable products other than those designated as Original FLINTEC Products NOTICE The contents of this manual are subject to change without notice Copyright 2007 by Fli...

Страница 3: ...4 MECHANICAL INSTALLATION 4 ELECTRICAL CONNECTIONS 4 LOAD CELL CABLE CONNECTION 5 OUTPUT CABLE CONNECTION 5 CORNER CORRECTION AT SCALES WITH FLINTEC LOAD CELLS 6 CLOSING THE JUNCTION BOX 6 SUMMARY OF...

Страница 4: ...h is more or less dry and protected from environmental stress The junction box itself has to be mounted with the cable glands showing vertically to the bottom A flooding or any tensile load on the cab...

Страница 5: ...ube significantly Unused cable inlets must be closed by the delivered blind plugs If the cable gland nuts are correctly tightened the sealing part of the cable gland must constrict the blind plug sign...

Страница 6: ...kg test load 0 1 kg 500 kg x 1100 0 22 Example 2 400 load cell 10 kg corner error with 5000 kg test load 10 kg 5000 kg x 400 0 8 4 Install the correction resistor into the junction box for the corresp...

Страница 7: ...ing hole must be closed by a blind plug and a gasket 6 The earth screw must be electrically connected with protective earth potential equalisation For doing this only the upper nut should be loosened...

Страница 8: ...ke service kit no 1 but without ring spanner SSG19 Service kit no 3 Article no 5200 U3 for load cells with maximum capacity in the range from 7 5 t to 22 5 t with ring spanner Parts list Description A...

Отзывы: