Concrete Spraying Machine 

– SSB 05.1 

 

 

 

Machine head (primary (upper) air), to the exhauster (secondary (bottom) air), to 
clean the Machine and control  the pneumatic vibrator. The controlling  cocks for 
the  air  intake  to  the  head  (primary  (upper)  air)  and  to  the  exhauster  (secondary 
(bottom) air) are equipped with manometers. 
 
The  central  lubrication  system  comprises  the  lubricating  equipment  and  tank, 
controlling automatic system, outputs and pipe. The lubrication system transports 
the lubricant (grease) or oil between the areas of sealing and wearing plates and so 
avoids their excessive friction. Type of plastics lubricator  –  A00 (Mogul, Madit, 
Slovnaft).  
 
The models without central lubrication system are equipped with the manual lever 
press lubricator for sealing and wearing plates. 
 
The control of the Machine is concentrated on the electric motor cover side. The 
compressed air intake is situated on the cover side.  
 
The whole Machine is placed on the frame with bantam wheels. Alternatively can 
be used a solid frame or a rail undercarriage. 
 
 

Working Principle 

 

The  concrete  spraying  machine  SSB  5.2  works  on  the  principle  of  pneumatic 
transport. 

 

Dry-gunning 

 
The  dry  mixture  for  spraying  or  transportation  is  poured  in  the  machine  and 
smoothly fills the cylinders of the  rotor below the hopper. To fill  a mixture into 
the rotor more easily, a vibrator and a rippling are fitted in the hopper.  
The  rotating  movement  of  the  rotor  moves  the  mixture  along  by  180  degrees  in 
the clockwise direction. The mixture is thus blown out from individual cylinders 
of  the  rotor  into  transport  hoses.  As  the  mix  passes  through  the  blower  into  the 
transport hoses, lower pressure air is added to enhance the continuous flow of the 
material  in  hoses.  The  hoses  are  equipped  with  the  spraying  nozzles  at  the  end, 
into which the mixing water is fed at the same time to wet the transported mixture. 
The required wetting of the mixture is controlled with the supply cock. 

Содержание SSB 05.1 DUO

Страница 1: ...ying Machine SSB 05 2 Series PRODUCER FILAMOS s r o Hate 546 261 01 Pribram Czech Republic Tel 420 318 637 763 Fax 420 318 624 181 www filamos com User Manual Concrete Spraying Machine SSB 05 1 DUO SS...

Страница 2: ...hine Operating 3 IV Description 6 V Technical Data 8 VI Accessories 10 VII Material 10 VIII Executions 10 IX Markings 11 X Testing 11 XI Delivery 12 XII Warranty 12 XIII Packaging 12 XIV Transport 12...

Страница 3: ...walls cooling towers water reservoirs sewerage plants etc during the construction and reconstruction of buildings and during the reinforcement and bracing of tunnel vaults and sewers The machine is de...

Страница 4: ...onditions of the machine at the same time Manipulation Machine can be transported by the suitable transport means defined by the site manager Total weight of the machine is 470 kg DUO 560 kg COM V wit...

Страница 5: ...han 18 years with theoretical and practical skills qualified to operate the machine Other Ways of Use The Machine cannot be used for any other purpose than transport of dry concrete mixes fire resista...

Страница 6: ...des The dozing drum is fixed on the top part of the bearing part shaft by a square end and tightening nut The Machine head is installed on the 4 tightening bolts The sealing plate is mounted on its bo...

Страница 7: ...take is situated on the cover side The whole Machine is placed on the frame with bantam wheels Alternatively can be used a solid frame or a rail undercarriage Working Principle The concrete spraying m...

Страница 8: ...tor revolutions 8 12 rpms min Performance parameter Parameter Rotor 1 9L Rotor 3 9L Rotor 6 9L Drum volume dm3 1 9 3 9 6 9 Drum rpm min 1 8 12 8 12 8 12 Theoretical output m3x h 1 0 8 1 2 1 8 2 7 3 3...

Страница 9: ...ax 100 Mains connection 3x400 V TN S Max deviation of voltage system 10 Coverage IP 55 The transporting distance and height are directly affected by The composition and water content of the conveyed m...

Страница 10: ...sealing plate 3 pcs Nozzle ending 2 pcs The set of accessories can be adjusted according to the customer s requirements length of hoses number of sealing plates etc VII Material The material used in...

Страница 11: ...ut rated voltage weight of machine Electric motor and gearbox have their own rating plates X Testing The properties of the machine are checked in the manufacturing plant by means of a functional test...

Страница 12: ...en changed modified or repaired without the manufacturer s previous consent If the machine has been damaged by incorrect electrical connection If the product has been damaged by a third person or vis...

Страница 13: ...following Standards have been used Directive of the European Community No 98 37 ES Mechanical Equipment Basic Requirements according to Appendix No 1 to NV 24 2003 Sb Czech National Standards SN EN I...

Страница 14: ...romagnetic valve 11 Main Air source 12 Automatic lubrication system 13 Electric energy connection 14 Remote control connection 15 Controlbox 16 Air vibrator 17 Hopper Optional components such as frequ...

Отзывы: