Concrete Spraying Machine 

– SSB 05.1 

 

 

 

 

IV.  Description 

 

The Machine comprises the following main parts: 
 

-

 

the Machine drive (electromotor, gearbox, speed variator, if any) 

-

 

basic frame 

-

 

dosing drum (rotor) with wearing plates 

-

 

the Machine head with upper sealing plate, lower sealing plate and exhauster, 

-

 

feeder and vibrator,  

-

 

rippling equipment, 

-

 

tightening bolts, 

-

 

exhauster with a filtration bag, 

-

 

air distribution and manometers, 

-

 

electrical installations, 

-

 

central lubricating system (if any), 

-

 

bantam wheels (rail undercarriage, frame), 

-

 

accessories  DN  25,  DN  32,  DN  40,  DN  50  (hoses,  quick  couplers,  nozzle, 
sealing plates, etc.) 

 

The Machine drive is executed by the slipping gear-box with: 
- 2-speed electric motor (DUO) 
- with 1-speed electric motor equipped with frequency invertor (COM-F) 
 
The  bearing  part  of  the  dosing  part,  the  Machine  drive  and  air  distribution  are 
situated on the frame. The bantam wheels are screwed on the basic frame sides. 
 
The dozing drum is fixed on the top part of the bearing part shaft by a square(end) 
and tightening nut.  
 
The  Machine  head  is  installed  on  the  4  tightening  bolts.  The  sealing  plate  is 
mounted on its bottom side and its bottom side rests on the dosing drum. The air 
intake  is  installed  on  the  Machine  head  upper  side  as  well  as  the  feeder  and 
exhaust with the filtration bag. 
 
The bottom sealing plate is fixed on the frame on which the dosing drum is rested 
as well as the exhauster and bottom exhaust. 
 
The Machine feeder is complimented by vibrator for acceleration of filling of the 
transported mix, and a sifter. 
 
The  Machine  head  is  mounted  on  by  four  tightening  bolts  serving  to  control 
(adjust) thrust of the sealing plates to the dozing drum. 
 
The exhausts with filtration bags serve to capture air remains  and dusty particles 
from the dosing drum cylinders. 
 
The  air  distribution  comprises  the  main  intake  and  four  controlling  cocks.  The 
main intake is provided with a controlling cock and quick coupler for connection 
of the pressured air  DN 40 hose. The controlling cocks serve to intake air to the 

Содержание SSB 05.1 DUO

Страница 1: ...ying Machine SSB 05 2 Series PRODUCER FILAMOS s r o Hate 546 261 01 Pribram Czech Republic Tel 420 318 637 763 Fax 420 318 624 181 www filamos com User Manual Concrete Spraying Machine SSB 05 1 DUO SS...

Страница 2: ...hine Operating 3 IV Description 6 V Technical Data 8 VI Accessories 10 VII Material 10 VIII Executions 10 IX Markings 11 X Testing 11 XI Delivery 12 XII Warranty 12 XIII Packaging 12 XIV Transport 12...

Страница 3: ...walls cooling towers water reservoirs sewerage plants etc during the construction and reconstruction of buildings and during the reinforcement and bracing of tunnel vaults and sewers The machine is de...

Страница 4: ...onditions of the machine at the same time Manipulation Machine can be transported by the suitable transport means defined by the site manager Total weight of the machine is 470 kg DUO 560 kg COM V wit...

Страница 5: ...han 18 years with theoretical and practical skills qualified to operate the machine Other Ways of Use The Machine cannot be used for any other purpose than transport of dry concrete mixes fire resista...

Страница 6: ...des The dozing drum is fixed on the top part of the bearing part shaft by a square end and tightening nut The Machine head is installed on the 4 tightening bolts The sealing plate is mounted on its bo...

Страница 7: ...take is situated on the cover side The whole Machine is placed on the frame with bantam wheels Alternatively can be used a solid frame or a rail undercarriage Working Principle The concrete spraying m...

Страница 8: ...tor revolutions 8 12 rpms min Performance parameter Parameter Rotor 1 9L Rotor 3 9L Rotor 6 9L Drum volume dm3 1 9 3 9 6 9 Drum rpm min 1 8 12 8 12 8 12 Theoretical output m3x h 1 0 8 1 2 1 8 2 7 3 3...

Страница 9: ...ax 100 Mains connection 3x400 V TN S Max deviation of voltage system 10 Coverage IP 55 The transporting distance and height are directly affected by The composition and water content of the conveyed m...

Страница 10: ...sealing plate 3 pcs Nozzle ending 2 pcs The set of accessories can be adjusted according to the customer s requirements length of hoses number of sealing plates etc VII Material The material used in...

Страница 11: ...ut rated voltage weight of machine Electric motor and gearbox have their own rating plates X Testing The properties of the machine are checked in the manufacturing plant by means of a functional test...

Страница 12: ...en changed modified or repaired without the manufacturer s previous consent If the machine has been damaged by incorrect electrical connection If the product has been damaged by a third person or vis...

Страница 13: ...following Standards have been used Directive of the European Community No 98 37 ES Mechanical Equipment Basic Requirements according to Appendix No 1 to NV 24 2003 Sb Czech National Standards SN EN I...

Страница 14: ...romagnetic valve 11 Main Air source 12 Automatic lubrication system 13 Electric energy connection 14 Remote control connection 15 Controlbox 16 Air vibrator 17 Hopper Optional components such as frequ...

Отзывы: