TWINFLEX
®
pro² Control Panel Engineering and Commissioning Manual
42
This active control will allow the engineer to change the type of ‘alarm
confirmation’ implemented. Use the
LEFT
and
RIGHT
keys to toggle
through the following options. Once the correct option has been
selected press the
ENTER
key.
1. SYSTEM – If any smoke detector on any
other zone
enters an alarm condition whilst a detector is
already in ‘alarm confirmation’, the panel will
override the delay and trigger a full alarm.
2. ZONAL – If any smoke detector on any other zone
enters an alarm condition whilst a detector is
already in ‘alarm confirmation’, then operation will
be as per the zone type for that zone. If the other
zone is set as an alarm confirmation dwell zone
then this will not trigger a full alarm, more than one
confirmation can be running at a time in this mode.
This active control will allow the engineer to set the ‘alarm confirmation’
delay timer. Press 1 – 5 to set the timer from 1 Minute to 5 Minutes,
then press
ENTER
to confirm the change.
This active control will allow the engineer to set an alarm delay for all
sounders and outputs on the selected zone. Use the
LEFT
and
RIGHT
keys to toggle through the following options. Once the correct option
has been selected, press the
ENTER
key.
1. INSTANT – When the panel receives a fire input,
all sounders and outputs on the zone
will immediately activate.
2. DELAYED – When the panel receives a fire input,
all sounders and outputs on the
selected zone will be delayed for the
time period set in the ‘Delay Timer’
menu.
7. Alarm configuration
2. Confirmation Type
7. Alarm configuration
3. Confirmation Delay
8. Alarm Delay
1. Delay Zone O/Ps
01/09/09 22:26 ENGR
OPTION : ZONAL
1.SYSTEM 2.ZONAL
Press <> OR Esc Key
01/09/09 22:26 ENGR
CONFIRMATION DELAY
DELAYS=1 (1-5 MIN)
Press Enter Key
01/09/09 22:26 ENGR
SET DELAY ZONE O/Ps
ENTER ZONE:00
Press Enter Key
01/09/09 22:26 ENGR
ZONE: INSTANT
1.INSTANT 2.DELAYED
Press <> OR Esc Key
www.acornfiresecurity.com