4.0 INSTALLATION
UL S2203
Cheetah Xi 50 Installation Manual
4-5
FM
P/N: 06-369
Rev 6, 09/2015
4.9
INSTALL INTERNAL PANEL COMPONENTS
Before installing the internal panel components into the enclosure back-box, thoroughly clean the enclosure
making sure that it is clean and free from any construction dust or debris. The Cheetah Xi 50 electronics
contain static sensitive components. Handle the electronics by the edges only and avoid touching the
integrated components. Keep the electronics in the protective static bags it was shipped in until time for
installation. Always ground yourself with a proper wrist strap before handling the module(s) to reduce the risk
of damage due to static discharge.
Note:
The mounting hardware for installing the panel components is shipped with the system enclosure.
4.9.1
INSTALL AC POWER TRANSFORMER
The following general steps shall be used to install the AC power transformer into the back-box:
1. Locate the four threaded press studs provided in the enclosure back-box for mounting the transformer
(See Exhibit 4-3).
2. Position the transformer over the press studs making sure that the transformer’s H1 and H2 (AC
primary input) terminals are facing to the left side of the enclosure. Secure the transformer in place
with four 6-32 hex nuts and lock-washers provided with the enclosure.
BACK-BOX
TRANSFORMER
Exhibit 4-3: Transformer Mounting Location
Exhibit 4-4: Transformer Mounting
Содержание 10-071
Страница 66: ...APPENDIX B B 2 Cheetah Xi 50 Installation Manual UL S2203 Rev 6 09 2015 P N 06 369 FM Reserved for future use ...
Страница 74: ...APPENDIX D D 2 Cheetah Xi 50 Installation Manual UL S2203 Rev 6 09 2015 P N 06 369 FM Reserved for future use ...
Страница 75: ......
Страница 76: ...704 SW 10 th Street P O Box 610 Blue Springs Missouri 64013 Tel 816 229 3405 Fax 816 229 0314 www fike com ...