DSMI-...
Festo DSMI-... 0102NH English
35
Electronic closed-loop operation of the DSMI-...:
Please note
Special commissioning conditions apply to electronic closed-loop operation.
S
When commissioning, take into account the instructions in the manuals for
the SPC... .
The following applies in all cases:
1. Tighten the two upstream one-way flow
control valves
– at first completely
– then loosen one turn.
2. Make sure that the operating conditions
lie within the permitted ranges.
3. Pressurize the drive in one of the following ways, as desired:
– slow pressurization of one side
– simultaneous pressurization of both sides with subsequent exhausting of
one side.
For slow pressurization when starting, use safety start-up valve type HEL-... or
HEM-... .
4. Start a test run.
5. During the test run, check to see if the following settings on the DSMI-... must
be modified:
– the swivel range of the moveable mass
– the swivel speed of the moveable mass.
6. Open the one-way flow control valves
slowly, until the desired swivel speed is
set.
The stop lever should reach the end posi-
tion, but not strike hard against it. If the
stop lever strikes the end position too
hard, it may jump back out of the end
position.
Fig. 30
Fig. 31
Содержание DSMI Series
Страница 104: ...DSMI Festo DSMI 0102NH Italiano 104...
Страница 130: ...DSMI Festo DSMI 0102NH 130...
Страница 131: ...DSMI Festo DSMI 0102NH 131...