4e Pull Arm Installation
1. Slide the pull arm roller into the track, then insert a track end cap on each end of the track and install track to door.
2. Attach the Pull Arm to the track roller with the roller locking screw and to the operator spindle loosely with the 8mm socket head
screw. Open the door to 90°, and tighten the 8mm socket head screw (see fig. 3).
3. Attach arm if required. Due to the mesh of the arm to operator spindle, the door may be open to slightly more or less than 90°. To
adjust arm, remove arm adjustment screws, push door open to 90° and reinstall arm screws (see fig. 4).
Pull Arm
Fig. 4
Fig. 3
Arm Locking
Screw
Arm Adjustment
Screws
8mm Socket
Head Screw
Pull Arm
Fig. 4
Fig. 3
Arm Locking
Screw
Arm Adjustment
Screws
8mm Socket
Head Screw
4f Remove the jumper from the control box Main Act and Main Act Com. The door should close.
4g Connect actuator wiring as required (see page 12).
4h Test the operator. (See Chapter 5: Operational Check on page 8)
4i Adjust the operator as required. (See Step 6: Operator Adustment on page 9)
4j Install the cover assembly onto the operator.
4k Release the operator for service. (See Step 7: Release for Service on page 11)